Providing and applying crystalline mortar by mixing in the ratio of 4.5 : 1 (4.5 parts crystalline mortar : 1 part water) for the treatment of faulty construction joints, cracks, tie rod holes and spalled & honeycombed surface of RCC underground structures like basement, water tanks, bridge deck etc. to ensure water tightness. The crystallie mortar shall conform to the EN 1504-3 having compressive strength Class R4 ≥45 MPa and adhesive bond strength Class R3 ≥1.5 MPa. The work shall be carried out all complete as per specification and the direction of the EngineerIn-Charge. The product performance shall carry guarantee for 10 years against any leakage
- Item number
- 22.25.1
- Analysis basis
- 1.00 meter
- Priced inputs
- 5
- Derived rate
- ₹547.70/ METER
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 22.25.1 (Providing and applying crystalline mortar by mixing in the ratio of 4.5 : 1 (4.5 parts crystalline mortar : 1 part water) for the treatment of faulty construction joints, cracks, tie rod holes and spalled & honeycombed surface of RCC underground structures like basement, water tanks, bridge deck etc. to ensure water tightness. The crystallie mortar shall conform to the EN 1504-3 having compressive strength Class R4 ≥45 MPa and adhesive bond strength Class R3 ≥1.5 MPa. The work shall be carried out all complete as per specification and the direction of the EngineerIn-Charge. The product performance shall carry guarantee for 10 years against any leakage For sealing cracks and faulty construction joints, routed out/making U-shape groove size 25x25mm and then primed the area with integral crystalline slurry @0.05kg/running metre and while the surface is tacky filled the groove upto surface with crystalline mortar @1.50kg/ running metre. Once crystalline mortar is touch dry then finally applied two coats of integral crystalline slurry @0.05kg/running metre per coat) is derived from 5 priced inputs for 1.00 meter and works out to ₹547.70 per meter after water charges, GST, CPOH and cess. The full build-up is below.
- MATERIAL :
- (3 x 0.05kg / meter) = 0.15kg
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0353 | MAT | Crystalline Mortar @1.50 kg per meterCrystalline mortar | kilogram | 1.5 | 209.00 | 313.50 |
| 0351 | MAT | Integral crystalline slurry for priming and finishingIntegral crystalline slurry | kilogram | 0.15 | 214.00 | 32.10 |
| 9999 | MAT | For making crystalline mortar and repair work etc.. | L.S. | 14.45 | 2.27 | 32.80 |
| 9999 | MAT | Sundries | L.S. | 1.15 | 2.27 | 2.61 |
| 9999 | MAT | Carriage of material and tools cost etc.. | L.S. | 1.75 | 2.27 | 3.97 |
- TOTAL
- 384.98
- Add 1 % Water charges on “W”
- +3.85
- TOTAL
- 388.83
- Add GST on “X” (multiplying factor 0.2127)
- +82.70
- TOTAL
- 471.53
- Add 15% CPOH on “Y”
- +70.73
- TOTAL
- 542.26
- Add Cess @ 1% on “Z”
- +5.42
- Cost for 1.00 meter
- 547.68
- SAY
- ₹547.70
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1862
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1862. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate