Providing and applying crystalline mortar by mixing in the ratio of 4.5 : 1 (4.5 parts crystalline mortar : 1 part water) for the treatment of faulty construction joints, cracks, tie rod holes and spalled & honeycombed surface of RCC underground structures like basement, water tanks, bridge deck etc. to ensure water tightness. The crystallie mortar shall conform to the EN 1504-3 having compressive strength Class R4 ≥45 MPa and adhesive bond strength Class R3 ≥1.5 MPa. The work shall be carried out all complete as per specification and the direction of the EngineerIn-Charge. The product performance shall carry guarantee for 10 years against any leakage

For sealing cracks and faulty construction joints, routed out/making U-shape groove size 25x25mm and then primed the area with integral crystalline slurry @0.05kg/running metre and while the surface is tacky filled the groove upto surface with crystalline mortar @1.50kg/ running metre. Once crystalline mortar is touch dry then finally applied two coats of integral crystalline slurry @0.05kg/running metre per coat
Item number
22.25.1
Analysis basis
1.00 meter
Priced inputs
5
Derived rate
₹547.70/ METER
D-01/RATE ANALYSISITEM 22.25.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 22.25.1 (Providing and applying crystalline mortar by mixing in the ratio of 4.5 : 1 (4.5 parts crystalline mortar : 1 part water) for the treatment of faulty construction joints, cracks, tie rod holes and spalled & honeycombed surface of RCC underground structures like basement, water tanks, bridge deck etc. to ensure water tightness. The crystallie mortar shall conform to the EN 1504-3 having compressive strength Class R4 ≥45 MPa and adhesive bond strength Class R3 ≥1.5 MPa. The work shall be carried out all complete as per specification and the direction of the EngineerIn-Charge. The product performance shall carry guarantee for 10 years against any leakage For sealing cracks and faulty construction joints, routed out/making U-shape groove size 25x25mm and then primed the area with integral crystalline slurry @0.05kg/running metre and while the surface is tacky filled the groove upto surface with crystalline mortar @1.50kg/ running metre. Once crystalline mortar is touch dry then finally applied two coats of integral crystalline slurry @0.05kg/running metre per coat) is derived from 5 priced inputs for 1.00 meter and works out to ₹547.70 per meter after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • MATERIAL :
  • (3 x 0.05kg / meter) = 0.15kg
ANALYSIS OF RATES · ITEM 22.25.1DETAILS OF COST FOR 1.00 METER
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0353MATCrystalline Mortar @1.50 kg per meterCrystalline mortarkilogram1.5209.00313.50
0351MATIntegral crystalline slurry for priming and finishingIntegral crystalline slurrykilogram0.15214.0032.10
9999MATFor making crystalline mortar and repair work etc..L.S.14.452.2732.80
9999MATSundriesL.S.1.152.272.61
9999MATCarriage of material and tools cost etc..L.S.1.752.273.97
BUILD-UP TO RATE
TOTAL
384.98
Add 1 % Water charges on “W”
+3.85
TOTAL
388.83
Add GST on “X” (multiplying factor 0.2127)
+82.70
TOTAL
471.53
Add 15% CPOH on “Y”
+70.73
TOTAL
542.26
Add Cess @ 1% on “Z”
+5.42
Cost for 1.00 meter
547.68
SAY
₹547.70
D-02/SOURCEPRINTED PAGE 1862
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1862

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1862. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.