Providing & Applying high quality acrylic modified resin based texture of Dholpur/Red sand stone Pattern with anti algae and UV resistance properties to be applied as intermediate finish in desired pattern @ 43.04 kg/10 sqm to form film of 11.5 mm thickness after scrapping and properly cleaning the surface to remove loose particles from the plaster surface, followed by top coating with Premium Acrylic Smooth exterior paint with Silicone additives of required shade by two or more coats @ 1.43 litre/10 sqm, complete as the direction of Engineer -inCharge

Item number
22.24A
Analysis basis
10 Sqm
Priced inputs
6
Derived rate
₹597.00/ SQM
D-01/RATE ANALYSISITEM 22.24A

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 22.24A (Providing & Applying high quality acrylic modified resin based texture of Dholpur/Red sand stone Pattern with anti algae and UV resistance properties to be applied as intermediate finish in desired pattern @ 43.04 kg/10 sqm to form film of 11.5 mm thickness after scrapping and properly cleaning the surface to remove loose particles from the plaster surface, followed by top coating with Premium Acrylic Smooth exterior paint with Silicone additives of required shade by two or more coats @ 1.43 litre/10 sqm, complete as the direction of Engineer -inCharge) is derived from 6 priced inputs for 10 Sqm and works out to ₹597.00 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 43.04 kg + 2.15 (Add wastage 5%) = 45.19 kg
  • Quantity taken for cost using once = 10 sqm
  • Top coat with premium acrylic exterior paint (two
  • or more coats)
ANALYSIS OF RATES · ITEM 22.24ADETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8513MATAcrylic modified resin based texturekg45.1950.002,259.50
SUBRate as per Item No.13.112.1 of SH:FinishingRate as per item 13.112.1sqm10131.301,313.00
9977MATCarriage of materialsL.S.3.92.278.85
0115LABCoolieday0.56736.00412.16
0123LABMason 1st classMason 1st classday0.56897.00502.32
9999MATSundries and scaffoldingL.S.402.2790.80
BUILD-UP TO RATE
TOTAL
4,586.63
Add 1 % Water charges on “W-A”
+32.74
TOTAL
4,619.37
Add GST on “X-A” (multiplying factor 0.2127)
+703.26
TOTAL
5,322.63
Add 15% CPOH on “Y-A”
+601.44
TOTAL
5,924.07
Add Cess @ 1% on “Z-A”
+46.11
Cost of 10 sqm
5,970.18
Cost of 1 sqm
597.02
SAY
₹597.00
D-02/SOURCEPRINTED PAGE 1861
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1861

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1861. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.