Providing and supplying Spandrel Glass Panels comprising of 6 mm thick heat strengthened monolithic float glass of approved colour and shade with reflective soft coating on surface # 2 of approved colour and shade so as to match the colour and shade of the IGUs in the vision panels etc. ,all complete for the required performances as specified, as per the Architectural drawings, as per the approved shop drawings, as specified, and as directed by the EngineerinCharge. For payment, only the actual area of glass on face # 1 of the glass panels (but excluding the area of grooves and weather silicone sealant) provided and fixed in position, shall be measured in sqm. (Payment for fixing of Spandrel Glass Panels in the curtain glazing is included in cost of relevent Item*).“(i) Coloured tinted float glass 6mm thick substrate with reflective soft coating on face # 2, having properties as visible Light transmittance (VLT) of 25 to 35 %, Light reflection internal 10 to 15%, light reflection external 10 to 20 %, shading coefficient (0.250.28) and U value of 3.0 to 3.3 W/m2 K etc. . The properties of performance glass shall be decided by technical sanctioning authority as per the site requirement
- Item number
- 25.6
- Analysis basis
- 3.23 sqm
- Priced inputs
- 4
- Derived rate
- ₹2,450.15/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 25.6 (Providing and supplying Spandrel Glass Panels comprising of 6 mm thick heat strengthened monolithic float glass of approved colour and shade with reflective soft coating on surface # 2 of approved colour and shade so as to match the colour and shade of the IGUs in the vision panels etc. ,all complete for the required performances as specified, as per the Architectural drawings, as per the approved shop drawings, as specified, and as directed by the EngineerinCharge. For payment, only the actual area of glass on face # 1 of the glass panels (but excluding the area of grooves and weather silicone sealant) provided and fixed in position, shall be measured in sqm. (Payment for fixing of Spandrel Glass Panels in the curtain glazing is included in cost of relevent Item*).“(i) Coloured tinted float glass 6mm thick substrate with reflective soft coating on face # 2, having properties as visible Light transmittance (VLT) of 25 to 35 %, Light reflection internal 10 to 15%, light reflection external 10 to 20 %, shading coefficient (0.250.28) and U value of 3.0 to 3.3 W/m2 K etc. . The properties of performance glass shall be decided by technical sanctioning authority as per the site requirement) is derived from 4 priced inputs for 3.23 sqm and works out to ₹2,450.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Width of the unit = 0.86 m
- Height of the unit = 3.75 m
- Area = 3.23 sqm
- Area i/c wastage @ 5 % = 3.39 sqm
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 2617 | MAT | 6 mm thick High performance glass | sqm | 3.39 | 1,056.00 | 3,579.84 |
| 9999 | MAT | Sundries (Insurance charges) | L.S. | 43.46 | 2.27 | 98.65 |
| 9999 | MAT | Sundries (Fabrication charges including silicon sealant, baker rod, desecant etc.) | L.S. | 682.55 | 2.27 | 1,549.39 |
| 9999 | MAT | Sundries (transporation including loading & unloading) | L.S. | 147.59 | 2.27 | 335.03 |
- TOTAL
- 5,562.91
- Add 1 % Water charges on “W”
- +55.63
- TOTAL
- 5,618.54
- Add GST on “X” (multiplying factor 0.2127)
- +1,195.06
- TOTAL
- 6,813.60
- Add 15% CPOH on “Y”
- +1,022.04
- TOTAL
- 7,835.64
- Add Cess @ 1% on “Z”
- +78.36
- Cost for 3.23 sqm
- 7,914.00
- Cost for 1 sqm
- 2,450.15
- SAY
- ₹2,450.15
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1902
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1902. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.