CPWD Analysis of Rates · Stone Work

Stone tile work for wall lining upto 10 m height with special adhesive over 12 mm thick bed of cement mortar 1:3 (1 cement : 3 coarse sand), including pointing in white cement with an admixture of pigment to match the stone shade 8mm thick (mirror polished and machine cut edge)

Raj Nagar plain white marble/ Udaipur green marble/ Zebra black marble

Item number
7.38.1.2
Analysis basis
Details of cost for 10sqm.
Priced inputs
9
Derived rate
2,766.45 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.38.1.2 Stone tile work for wall lining upto 10 m height with special adhesive over 12 mm thick bed of cement mortar 1:3 (1 cement : 3 coarse sand), including pointing in white cement with an admixture of pigment to match the stone shade 8mm thick (mirror polished and machine cut edge) Raj Nagar plain white marble/ Udaipur green marble/ Zebra black marble — is derived from 9 priced inputs and works out to ₹2,766.45 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • 8mm thick Raj Nagar white stone tile
  • = 10.00sqm.+ Add 2.5% wastage =
  • 0.25sqm. Total = 10.25sqm
  • Cement mortar 1:3 (1 cement : 3 coarse
  • sand)
  • slurry @ 3.3 kg/sqm
  • Labour for placing and fixing :
CodeInputUnitQuantityRate (INR)Amount (INR)
74398mm thick (mirror polished tiles machine cut edge) Raj Nagar white8 mm thick (mirror polished tiles machine cut edge) Raj Nagar whiteMaterialsqm10.25477.004,889.25
9977Carriage of Raj Nagar white stone tilesMaterialL.S.40.042.2790.89
Rate as per Item Number 3.8 of SH: MortarsRate as per item 3.8Sub-analysiscum0.144,881.95683.47
0367Portland CementPortland Cement (OPC-43 Grade)Materialtonne0.0335,156.00170.15
9999Mortar for pointing in white cementMaterialL.S.25.742.2758.43
0123Mason 1st classMason 1st classLabourday7.7897.006,906.90
0114BeldarLabourday7.7736.005,667.20
9999Granular sand particles mixed with araldite to be pasted on each side to form interlocking arrangement with cement plasterMaterialL.S.2602.27590.20
9999SundriesMaterialL.S.171.62.27389.53
TOTAL
19,446.02
Add 1 % Water charges on “W”
194.46
TOTAL
19,640.48
Add GST on “X” (multiplying factor 0.2127)
4,177.53
TOTAL
23,818.01
Add 15% CPOH on “Y”
3,572.70
TOTAL
27,390.71
Add Cess @ 1% on “Z”
273.91
Cost for 10 sqm.
27,664.62
Cost of 1 sqm.
2,766.46
Say
2,766.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 379. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.