Providing and fixing sloping chajja of stone 40 mm thick and upto 80 cm wide beyond the wall as measured along the slope in cement mortar 1:4 (1 cement : 4 coarse sand) with 12 mm diameter anchoring steel bar, 45 cm long, fixed in each stone and supported on and including with bricks cove in cement mortar 1:4 (1 cement : 4 coarse sand), including pointing in cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : White sand stone

With common burnt clay F.P.S.(non modular) bricks of class designation 7.5
Item number
7.28.2.1
Analysis basis
a chajja
Priced inputs
12
Derived rate
₹2,932.60/ SQM
D-01/RATE ANALYSISITEM 7.28.2.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.28.2.1 (Providing and fixing sloping chajja of stone 40 mm thick and upto 80 cm wide beyond the wall as measured along the slope in cement mortar 1:4 (1 cement : 4 coarse sand) with 12 mm diameter anchoring steel bar, 45 cm long, fixed in each stone and supported on and including with bricks cove in cement mortar 1:4 (1 cement : 4 coarse sand), including pointing in cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : White sand stone : With common burnt clay F.P.S.(non modular) bricks of class designation 7.5) is derived from 12 priced inputs for a chajja and works out to ₹2,932.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (finished work)
  • Chisel dressed 80cm sloping length plus
  • 20cm bearing Area = 2.5x1.00=2.50sqm
  • Labour for dressing:
  • Anchoring steel bars 12mm dia. 45cm
  • long, 5 Nos. @ 0.80kg/m = 0.02q
  • Mortar for pointing 1:2 (1 Cement : 2
  • Stone dust)
  • Brick cover support 4 courses with bricks
  • of class designation 75
  • 4x7+5+5=38cm girth 2.5m length
  • =38cmx2.5m=95cm
  • Brick work in triangular gap above cover
  • with bricks of class designation 5 in cement mortar 1:4
  • 1/2x2.5x0.2x0.07=0.018cum.
ANALYSIS OF RATES · ITEM 7.28.2.1DETAILS OF COST FOR A CHAJJA 2.00 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1165MATWhite sand stone slab 40 mm thick (undressed)White sand stone slab 40 mm thick (un-dressed)sqm2.75370.001,017.50
0125LABMason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classday0.5816.00408.00
1002MATMild steel round bar 12 mm dia and belowquintal0.025,550.00111.00
9999MATCutting threads and cost of nuts, washers, etcL.S.67.342.27152.86
SUBRate as per Item Number 3.12 of SH: MortarsRate as per item 3.12cum0.0095,252.0047.27
9999MATPigmentL.S.6.242.2714.16
9999MATExtra cost of white cementL.S.26.912.2761.09
0125LABMason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classday1816.00816.00
0114LABBeldarday1.5736.001,104.00
9999MATScaffolding and sundries etc.L.S.16.122.2736.59
9999MATCost for Brick cover support .L.S.1042.27236.08
SUBRate as per item No 6.4.1 of SH :- Brick workRate as per item 6.4.1cum0.0189,344.35168.20
BUILD-UP TO RATE
TOTAL
4,172.75
Add 1 % Water charges on “W-A”
+40.05
TOTAL
4,212.80
Add GST on “X-A” (multiplying factor 0.2127)
+860.29
TOTAL
5,073.09
Add 15% CPOH on “Y-A”
+735.73
TOTAL
5,808.82
Add Cess @ 1% on “Z-A”
+56.41
Cost of 2 sqm.
5,865.23
Cost of 1 sqm.
2,932.62
SAY
₹2,932.60
D-02/SOURCEPRINTED PAGE 371
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
371

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 371. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSTONE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.