Skip to main content

CPWD Analysis of Rates · Stone Work

1:6 (1 white cement : 6 coarse sand) including pointing with white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade. One face dressed Red sand stone

Item number
7.15.1.1
Analysis basis
Details of cost for 10 cudm or 0.01 cum
Priced inputs
15
Derived rate
64,926.00 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.15.1.1 1:6 (1 white cement : 6 coarse sand) including pointing with white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade. One face dressed Red sand stone — is derived from 15 priced inputs for 10 cudm and works out to ₹64,926.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Finished work = 10 cudm.+ Add wastage
  • @ 33.3% = 3.33 cudm. Total = 13.33
  • cudm.
  • Dressing charges
  • Fixing charges
  • Extra labour for lifting of materials upto
  • floor V level (0.01x1.50 = 0.015)
CodeInputUnitQuantityRate (INR)Amount (INR)
1160Red sand stone blockMaterial10 cudm1.333130.00173.29
0125Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabourday0.059816.0048.14
0102Blacksmith 1st classLabourday0.006897.005.38
0114BeldarLabourday0.044736.0032.38
0115CoolieLabourday0.022736.0016.19
0100BandhaniLabourday0.044816.0035.90
0125Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabourday0.044816.0035.90
0102Blacksmith 1st classLabourday0.006897.005.38
0114BeldarLabourday0.022736.0016.19
0115CoolieLabourday0.022736.0016.19
0100BandhaniLabourday0.022816.0017.95
0101BhistiLabourday0.022816.0017.95
9999ScaffoldingMaterialL.S.2.732.276.20
9999Mortar for laying and pointingMaterialL.S.8.062.2718.30
0115CoolieLabourday0.015736.0011.04
TOTAL
456.38
Add 1 % Water charges on “W”
4.56
TOTAL
460.94
Add GST on “X” (multiplying factor 0.2127)
98.04
TOTAL
558.98
Add 15% CPOH on “Y”
83.85
TOTAL
642.83
Add Cess @ 1% on “Z”
6.43
Cost of 10 cudm.
649.26
Cost of 1 cum.
64,926.00
Say
64,926.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 361. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works