CPWD Analysis of Rates · Stone Work

Stone work plain ashlar in domes , in super structure upto floor V level in cement mortar 1:3 (1 cement : 3 coarse sand) including centering, shuttering and pointing with white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade Both face dressed

White sand stone

Item number
7.14.2.2
Analysis basis
Details of cost for 10 cudm or 0.01 cum
Priced inputs
18
Derived rate
1,84,177.00 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.14.2.2 Stone work plain ashlar in domes , in super structure upto floor V level in cement mortar 1:3 (1 cement : 3 coarse sand) including centering, shuttering and pointing with white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade Both face dressed White sand stone — is derived from 18 priced inputs for 10 cudm and works out to ₹1,84,177.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Finished work = 10 cudm.+ Add wastage
  • @ 33.3% = 3.33 cudm. Total = 13.33
  • cudm.
  • Dressing charges
  • Fixing charges
  • Extra labour for lifting of material up to
  • floor five level (0.01 x 1.5 = 0.015)
CodeInputUnitQuantityRate (INR)Amount (INR)
1161White sand stone blockMaterial10 cudm1.333205.00273.27
0125Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabourday0.352816.00287.23
0102Blacksmith 1st classLabourday0.012897.0010.76
0126Mason (for ornamental stone work) 1st classLabourday0.352897.00315.74
0114BeldarLabourday0.088736.0064.77
0115CoolieLabourday0.044736.0032.38
0100BandhaniLabourday0.088816.0071.81
0125Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabourday0.044816.0035.90
0102Blacksmith 1st classLabourday0.006897.005.38
0114BeldarLabourday0.022736.0016.19
0115CoolieLabourday0.022736.0016.19
0100BandhaniLabourday0.022816.0017.95
0101BhistiLabourday0.022816.0017.95
9999ScaffoldingMaterialL.S.2.732.276.20
9999Mortar for laying and pointingMaterialL.S.8.062.2718.30
9999Centring and shutteringMaterialL.S.33.152.2775.25
9999Extra for using white cementMaterialL.S.8.062.2718.30
0115CoolieLabourday0.015736.0011.04
TOTAL
1,294.61
Add 1 % Water charges on “W”
12.95
TOTAL
1,307.56
Add GST on “X” (multiplying factor 0.2127)
278.12
TOTAL
1,585.68
Add 15% CPOH on “Y”
237.85
TOTAL
1,823.53
Add Cess @ 1% on “Z”
18.24
Cost of 10 cudm.
1,841.77
Cost of 1 cum.
1,84,177.00
Say
1,84,177.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 360. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.