Skip to main content

CPWD Analysis of Rates · Stone Work

Stone work in plain ashlar in super structure upto floor five level in cement mortar 1:6 (1 cement : 6 coarse sand) including pointing with cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : Both face dressed

White sand stone

Item number
7.12.2.2
Analysis basis
Details of cost for 10 cudm or 0.01 cum
Priced inputs
15
Derived rate
1,05,519.00 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.12.2.2 Stone work in plain ashlar in super structure upto floor five level in cement mortar 1:6 (1 cement : 6 coarse sand) including pointing with cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : Both face dressed White sand stone — is derived from 15 priced inputs for 10 cudm and works out to ₹1,05,519.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Finished work = 10 cudm.+ Add wastage
  • @ 33.3% = 3.33 cudm. Total = 13.33
  • cudm.
  • Extra labour for lifting of materials upto
  • floor V level. (0.01 x 1.50 =0.015)
  • Dressing charges
  • Fixing charges
CodeInputUnitQuantityRate (INR)Amount (INR)
1161White sand stone blockMaterial10 cudm1.333205.00273.27
0115CoolieLabourday0.015736.0011.04
0125Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabourday0.176816.00143.62
0102Blacksmith 1st classLabourday0.012897.0010.76
0114BeldarLabourday0.088736.0064.77
0115CoolieLabourday0.044736.0032.38
0100BandhaniLabourday0.088816.0071.81
0125Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabourday0.044816.0035.90
0102Blacksmith 1st classLabourday0.006897.005.38
0114BeldarLabourday0.022736.0016.19
0115CoolieLabourday0.022736.0016.19
0100BandhaniLabourday0.022816.0017.95
0101BhistiLabourday0.022816.0017.95
9999ScaffoldingMaterialL.S.2.732.276.20
9999Mortar for laying and pointingMaterialL.S.8.062.2718.30
TOTAL
741.71
Add 1 % Water charges on “W”
7.42
TOTAL
749.13
Add GST on “X” (multiplying factor 0.2127)
159.34
TOTAL
908.47
Add 15% CPOH on “Y”
136.27
TOTAL
1,044.74
Add Cess @ 1% on “Z”
10.45
Cost of 10 cudm.
1,055.19
Cost of 1 cum.
1,05,519.00
Say
1,05,519.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 353. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works