Skip to main content
R/DAR 2023

Extra for providing mechanical device chain and crank operation for operating rolling shutters

Exceeding 16.80 sqm in area
Item number
10.8.2
Analysis basis
one sqm
Priced inputs
2
Derived rate
₹1,181.80/ SQM
D-01/RATE ANALYSISITEM 10.8.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.8.2 (Extra for providing mechanical device chain and crank operation for operating rolling shutters Exceeding 16.80 sqm in area) is derived from 2 priced inputs for one sqm and works out to ₹1,181.80 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 10.8.2DETAILS OF COST FOR ONE SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0978MATExtra for mechanical devices chain and cranked operation for operating rolling shutters : exceeding 16.80 sq.m area of doorExtra for mechanical devices chain and cranked operation for operating rolling shutters: exceeding 16.80 sqm area of doorsqm1800.00800.00
9999MATSundriesL.S.13.522.2730.69
BUILD-UP TO RATE
TOTAL
830.69
Add 1 % Water charges on “W”
+8.31
TOTAL
839.00
Add GST on “X” (multiplying factor 0.2127)
+178.46
TOTAL
1,017.46
Add 15% CPOH on “Y”
+152.62
TOTAL
1,170.08
Add Cess @ 1% on “Z”
+11.70
Cost of 1 sqm.
1,181.78
SAY
₹1,181.80
D-02/SOURCEPRINTED PAGE 723
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
723

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 723. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSTEEL WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.