Providing and fixing 1mm thick M.S. sheet door with frame of 40x40x6 mm angle iron and 3 mm M.S. gusset plates at the junctions and corners, all necessary fittings complete, including applying a priming coat of approved steel primer

Using flats 30x6mm for diagonal braces and central cross piece
Item number
10.5.2
Analysis basis
a double
Priced inputs
17
Derived rate
₹5,563.75/ A DOUBLE
D-01/RATE ANALYSISITEM 10.5.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.5.2 (Providing and fixing 1mm thick M.S. sheet door with frame of 40x40x6 mm angle iron and 3 mm M.S. gusset plates at the junctions and corners, all necessary fittings complete, including applying a priming coat of approved steel primer Using flats 30x6mm for diagonal braces and central cross piece) is derived from 17 priced inputs for a double and works out to ₹5,563.75 per a double after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 2.4x2.4m = 5.76sqm.
  • (i) M.S. sheet 1mm thick
  • 5.76sqm. @ 7.85kg/sqm. = 45.216kg.+
  • Total = 49.738kg = 0.497 q
  • (ii) Gussets plates-3.00mm thick vide (ii)
  • in item 10.6 = 0.5910sqm.+
  • at mid height = 4x0.0528 = 0.2112sqm.
  • Total = 0.8022sqm.+
  • Total =0.8824sqm.@ 23.55 kg/sqm =20.78
  • kg
  • Grand Total=0.2078 qtl say 0.208 qtl
  • (iii) Angle iron:40x40x6mm @3.5kg/m
  • Sides-4x2.40 = 9.6m+
  • Top & bottom-4x1.20=4.8m+
  • Total = 14.40m+
  • Total = 15.84m
  • 15.84m @ 3.5kg. per m. = 55.44kg
  • = 0.554qtl
  • (iv) Flats 30x6mm @1.4kg/m
  • 4x2.45=9.80m+
  • 2x1.20=2.40m
  • Total = 12.20m+
  • Total = 13.42m
  • 13.42m @ 1.4kg. per m. = 18.8kg.
  • = 0.188q
  • Carriage of (i) (ii) and (iv)
  • 0.0497+0.0208+0.0554+0.0188=0.1447
  • tonne say 0.145 tonne
  • Applying priming coatM.S. sheet = 11.52
  • Angle iron-0.16x24.3 = 3.89
  • 0.16x14.40 = 2.30+
  • Flats 0.072x12.2 = 0.88
  • Total = 14.70sqm.
  • Add wastage @ 10% = 4.522kg.
  • Add wastage @ 10% = 0.0802sqm.
  • Add wastage @ 10% = 1.44m
  • Add wastage @ 10% = 1.22m
ANALYSIS OF RATES · ITEM 10.5.2DETAILS OF COST FOR A DOUBLE LEAF DOOR OF SIZE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1013MATMild steel sheets for tanksMild steel sheets of 1.00 mm thickness for tanksquintal0.4975,500.002,733.50
1010MATMild steel platesquintal0.2085,700.001,185.60
1007MATStructurals such as tees,angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joistsquintal0.5545,965.003,304.61
1008MATFlats upto 10 mm in thicknessFlats up to 10 mm in thicknessquintal0.1885,450.001,024.60
1036MATIron pintels including welded pineach437.00148.00
1222MATMild steel sheets with bolts and nuts to rest on pintelseach4120.00480.00
1019MATMild steel hookseach232.0064.00
9999MATLocking arrangements and handlesL.S.167.72.27380.68
9999MATRivetsL.S.269.12.27610.86
SUBRate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3sqm14.767.40990.78
0116LABFitter (grade 1)day2897.001,794.00
0102LABBlacksmith 1st classday3897.002,691.00
0103LABBlacksmith 2nd classday4816.003,264.00
0123LABMason 1st classMason 1st classday0.06897.0053.82
0124LABMason 2nd classMason 2nd classday0.06816.0048.96
0114LABBeldarday5736.003,680.00
9999MATSundriesL.S.161.462.27366.51
BUILD-UP TO RATE
TOTAL
22,820.92
Add 1 % Water charges on “W-A”
+218.30
TOTAL
23,039.22
Add GST on “X-A” (multiplying factor 0.2127)
+4,689.70
TOTAL
27,728.92
Add 15% CPOH on “Y-A”
+4,010.72
TOTAL
31,739.64
Add Cess @ 1% on “Z-A”
+307.49
Cost of 5.76 sqm.
32,047.13
Cost per sqm.
5,563.74
SAY
₹5,563.75
D-02/SOURCEPRINTED PAGE 719
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
719

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 719. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.