Skip to main content
R/DAR 2023

Providing and fixing 1 mm thick M.S. sheet sliding-shutters, with frame and diagonal braces of 40x40x6 mm angle iron, 3 mm M.S. gusset plates at the junctions and corners, 25 mm dia pulley, 40x40x6 mm angle and Tiron guide at the top and bottom respectively, including applying a priming coat of approved steel primer

Item number
10.4
Analysis basis
one double
Priced inputs
17
Derived rate
₹6,566.20/ ONE DOUBLE
D-01/RATE ANALYSISITEM 10.4

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.4 (Providing and fixing 1 mm thick M.S. sheet sliding-shutters, with frame and diagonal braces of 40x40x6 mm angle iron, 3 mm M.S. gusset plates at the junctions and corners, 25 mm dia pulley, 40x40x6 mm angle and Tiron guide at the top and bottom respectively, including applying a priming coat of approved steel primer) is derived from 17 priced inputs for one double and works out to ₹6,566.20 per one double after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 2.4x2.4m = 5.76sqm.
  • (i) M.S. sheet 1mm thick
  • 5.76sqm. @ 7.85kg/sqm. = 45.216kg.+
  • Total = 49.738kg = 0.497 q
  • (ii) Gusset plates 3.00mm thick
  • Area of one gusset plates
  • 0.3x0.04 = 0.0120+
  • 1/2x0.26(0.04+0.3) = 0.0442
  • Total = 0.0562sqm.+
  • 8x0.0562 = 0.4496sqm.+
  • 2x22/7x1/4x0.3x0.3=0.1414sqm.
  • Total = 0.5910sqm.
  • 0.5910sqm.@23.55kg/sqm.=13.92kg.+
  • Total = 15.31kg. or 0.153q
  • (iii) Angle iron
  • 40x40x6mm @ 3.5kg/m
  • Sides-4x2.4=9.6m+
  • Bottom & top 4x1.2 = 4.8m+
  • Diagonals-2x2.5=5.0m+
  • 2x2.45 = 4.9m+
  • Top and bottom guides
  • 2x4.8 = 9.6m
  • Top guide supports
  • 7x0.8 = 2.1m
  • Total = 36.0m
  • 36m @3.5kg. per m. = 126kg.+
  • Total = 138.6kg. or 1.39q
  • Channel 25x25x6mm @ 3.05kg/m
  • Bottom-2.4m : 2.4x3.05
  • Channel 40x40x6mm @ 5.56kg/m
  • 0.5x5.56 = 2.78kg.
  • Total = 10.1kg.+
  • Total = 11.11kg. or 0.11q
  • Priming coatM.S. Sheet 2x5.76 = 11.52+
  • Angle iron 0.16x36 = 5.76+
  • Channel-0.15x2.4=0.36+
  • 0.24x0.5=0.12
  • Total = 17.76 Say 18.0sqm.
  • Add wastage @ 10% = 4.522kg.
  • Add wastage @ 10% = 1.39kg
  • Add wastage @ 10% = 12.6kg.
  • Add wastage @ 10% = 1.101kg.
ANALYSIS OF RATES · ITEM 10.4DETAILS OF COST FOR ONE DOUBLE LEAF DOOR SIZE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1013MATMild steel sheets for tanksMild steel sheets of 1.00 mm thickness for tanksquintal0.4975,500.002,733.50
1010MATMild steel platesquintal0.1535,700.00872.10
1007MATStructurals such as tees,angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joistsquintal1.395,965.008,291.35
1007MATStructurals such as tees,angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joistsquintal0.115,965.00656.15
9999MAT(iv) Pully guide blocks including drilling holesL.S.269.12.27610.86
0969MATPully 25 mm diaPulley 25 mm diaeach848.00384.00
9999MAT(vi) Handles and locking arrangementsL.S.167.752.27380.79
9999MAT(vii) Bolts and rivetsL.S.269.12.27610.86
9999MAT(viii)Cement concreteL.S.13.522.2730.69
SUBRate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3sqm1867.401,213.20
0116LABFitter (grade 1)day2897.001,794.00
0102LABBlacksmith 1st classday3897.002,691.00
0103LABBlacksmith 2nd classday4816.003,264.00
0114LABBeldarday4736.002,944.00
0123LABMason 1st classMason 1st classday0.06897.0053.82
0124LABMason 2nd classMason 2nd classday0.06816.0048.96
9999MATSundriesL.S.161.462.27366.51
BUILD-UP TO RATE
TOTAL
26,945.79
Add 1 % Water charges on “W-A”
+257.33
TOTAL
27,203.12
Add GST on “X-A” (multiplying factor 0.2127)
+5,528.06
TOTAL
32,731.18
Add 15% CPOH on “Y-A”
+4,727.70
TOTAL
37,458.88
Add Cess @ 1% on “Z-A”
+362.46
Cost of 5.76 sqm.
37,821.34
Cost per sqm.
6,566.20
SAY
₹6,566.20
D-02/SOURCEPRINTED PAGE 716
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
716

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 716. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSTEEL WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.