Skip to main content

CPWD Analysis of Rates · Steel Work

Providing and fixing 1 mm thick M.S. sheet sliding-shutters, with frame and diagonal braces of 40x40x6 mm angle iron, 3 mm M.S. gusset plates at the junctions and corners, 25 mm dia pulley, 40x40x6 mm angle and Tiron guide at the top and bottom respectively, including applying a priming coat of approved steel primer

Item number
10.4
Analysis basis
Details of cost for one double leaf door size
Priced inputs
17
Derived rate
6,566.20 / one double

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.4 Providing and fixing 1 mm thick M.S. sheet sliding-shutters, with frame and diagonal braces of 40x40x6 mm angle iron, 3 mm M.S. gusset plates at the junctions and corners, 25 mm dia pulley, 40x40x6 mm angle and Tiron guide at the top and bottom respectively, including applying a priming coat of approved steel primer — is derived from 17 priced inputs for one double and works out to ₹6,566.20 per one double after water charges, GST, CPOH and cess. The full build-up is below.

  • 2.4x2.4m = 5.76sqm.
  • (i) M.S. sheet 1mm thick
  • 5.76sqm. @ 7.85kg/sqm. = 45.216kg.+
  • Total = 49.738kg = 0.497 q
  • (ii) Gusset plates 3.00mm thick
  • Area of one gusset plates
  • 0.3x0.04 = 0.0120+
  • 1/2x0.26(0.04+0.3) = 0.0442
  • Total = 0.0562sqm.+
  • 8x0.0562 = 0.4496sqm.+
  • 2x22/7x1/4x0.3x0.3=0.1414sqm.
  • Total = 0.5910sqm.
  • 0.5910sqm.@23.55kg/sqm.=13.92kg.+
  • Total = 15.31kg. or 0.153q
  • (iii) Angle iron
  • 40x40x6mm @ 3.5kg/m
  • Sides-4x2.4=9.6m+
  • Bottom & top 4x1.2 = 4.8m+
  • Diagonals-2x2.5=5.0m+
  • 2x2.45 = 4.9m+
  • Top and bottom guides
  • 2x4.8 = 9.6m
  • Top guide supports
  • 7x0.8 = 2.1m
  • Total = 36.0m
  • 36m @3.5kg. per m. = 126kg.+
  • Total = 138.6kg. or 1.39q
  • Channel 25x25x6mm @ 3.05kg/m
  • Bottom-2.4m : 2.4x3.05
  • Channel 40x40x6mm @ 5.56kg/m
  • 0.5x5.56 = 2.78kg.
  • Total = 10.1kg.+
  • Total = 11.11kg. or 0.11q
  • Priming coatM.S. Sheet 2x5.76 = 11.52+
  • Angle iron 0.16x36 = 5.76+
  • Channel-0.15x2.4=0.36+
  • 0.24x0.5=0.12
  • Total = 17.76 Say 18.0sqm.
  • Add wastage @ 10% = 4.522kg.
  • Add wastage @ 10% = 1.39kg
  • Add wastage @ 10% = 12.6kg.
  • Add wastage @ 10% = 1.101kg.
CodeInputUnitQuantityRate (INR)Amount (INR)
1013Mild steel sheets for tanksMild steel sheets of 1.00 mm thickness for tanksMaterialquintal0.4975,500.002,733.50
1010Mild steel platesMaterialquintal0.1535,700.00872.10
1007Structurals such as tees,angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joistsMaterialquintal1.395,965.008,291.35
1007Structurals such as tees,angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joistsMaterialquintal0.115,965.00656.15
9999(iv) Pully guide blocks including drilling holesMaterialL.S.269.12.27610.86
0969Pully 25 mm diaPulley 25 mm diaMaterialeach848.00384.00
9999(vi) Handles and locking arrangementsMaterialL.S.167.752.27380.79
9999(vii) Bolts and rivetsMaterialL.S.269.12.27610.86
9999(viii)Cement concreteMaterialL.S.13.522.2730.69
Rate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3Sub-analysissqm1867.401,213.20
0116Fitter (grade 1)Labourday2897.001,794.00
0102Blacksmith 1st classLabourday3897.002,691.00
0103Blacksmith 2nd classLabourday4816.003,264.00
0114BeldarLabourday4736.002,944.00
0123Mason 1st classMason 1st classLabourday0.06897.0053.82
0124Mason 2nd classMason 2nd classLabourday0.06816.0048.96
9999SundriesMaterialL.S.161.462.27366.51
TOTAL
26,945.79
Add 1 % Water charges on “W-A”
257.33
TOTAL
27,203.12
Add GST on “X-A” (multiplying factor 0.2127)
5,528.06
TOTAL
32,731.18
Add 15% CPOH on “Y-A”
4,727.70
TOTAL
37,458.88
Add Cess @ 1% on “Z-A”
362.46
Cost of 5.76 sqm.
37,821.34
Cost per sqm.
6,566.20
Say
6,566.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 716. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works