Providing and fixing in position collapsible steel shutters with vertical channels 20x10x2 mm and braced with flat iron diagonals 20x5 mm size, with top and bottom rail of T-iron 40x40x6 mm, with 40 mm dia steel pulleys, complete with bolts, nuts, locking arrangement, stoppers, handles, including applying a priming coat of approved steel primer

Item number
10.3
Analysis basis
Details of cost for a gate 2.4mx1.5m =
Priced inputs
14
Derived rate
11,439.60 / a gate

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.3 Providing and fixing in position collapsible steel shutters with vertical channels 20x10x2 mm and braced with flat iron diagonals 20x5 mm size, with top and bottom rail of T-iron 40x40x6 mm, with 40 mm dia steel pulleys, complete with bolts, nuts, locking arrangement, stoppers, handles, including applying a priming coat of approved steel primer — is derived from 14 priced inputs for a gate and works out to ₹11,439.60 per a gate after water charges, GST, CPOH and cess. The full build-up is below.

  • 3.6sqm.
  • M.S. channels 18 Nos. on both sides
  • 20x10x2mm @ 0.56kg/m
  • 2x18x2.4 = 86.40m+
  • Total = 95.04m
  • 95.04m@0.56kg/m =53.22kg=0.53q
  • M.S. Tee-40x40x6mm
  • for bottom-1.570m+
  • for top = 1.725m
  • Total =3.295m Say 3.3m
  • 3.3m @ 3.5kg/m = 11.55kg+
  • Total = 12.705Kg. Say 0.13q
  • 20mmx5mm flat iron diagonals 4 Nos.
  • 4x32x0.5334 = 68.275m
  • 68.275m @ 0.8kg/m = 54.62kg+
  • Total = 60.08kg = 0.60q
  • Priming coatChannel - 36x0.076x2.4 = 6.57sqm.+
  • Tee-0.16x3.3 = 0.53sqm.+
  • Flats-0.05x68 = 3.40sqm.
  • Total = 10.50sqm.
  • Add wastage @ 10% = 8.64m
  • Add wastage @ 10% = 1.155 Kg.
  • Add wastage @10% = 5.46kg
CodeInputUnitQuantityRate (INR)Amount (INR)
1007Structurals such as tees,angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joistsMaterialquintal0.535,965.003,161.45
1007Structurals such as tees,angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joistsMaterialquintal0.135,965.00775.45
1008Flats upto 10 mm in thicknessFlats up to 10 mm in thicknessMaterialquintal0.65,450.003,270.00
9999Cost of rivets fixing hooks and washersMaterialL.S.269.12.27610.86
9999Cost of locking arrangements and handlesMaterialL.S.67.342.27152.86
4013Pully 40 mm diaPulley 40 mm diaMaterialeach1040.00400.00
Rate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3Sub-analysissqm10.567.40707.70
0116Fitter (grade 1)Labourday3897.002,691.00
0102Blacksmith 1st classLabourday6897.005,382.00
0103Blacksmith 2nd classLabourday6816.004,896.00
0123Mason 1st classMason 1st classLabourday0.5897.00448.50
0124Mason 2nd classMason 2nd classLabourday0.5816.00408.00
0114BeldarLabourday8736.005,888.00
9999SundriesMaterialL.S.161.462.27366.51
TOTAL
29,158.33
Add 1 % Water charges on “W-A”
284.51
TOTAL
29,442.84
Add GST on “X-A” (multiplying factor 0.2127)
6,111.96
TOTAL
35,554.80
Add 15% CPOH on “Y-A”
5,227.07
TOTAL
40,781.87
Add Cess @ 1% on “Z-A”
400.74
Cost of 3.6sqm.
41,182.61
Cost per sqm.
11,439.61
Say
11,439.60

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 715. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.