CPWD Analysis of Rates · Steel Work
Providing and fixing in position collapsible steel shutters with vertical channels 20x10x2 mm and braced with flat iron diagonals 20x5 mm size, with top and bottom rail of T-iron 40x40x6 mm, with 40 mm dia steel pulleys, complete with bolts, nuts, locking arrangement, stoppers, handles, including applying a priming coat of approved steel primer
- Item number
- 10.3
- Analysis basis
- Details of cost for a gate 2.4mx1.5m =
- Priced inputs
- 14
- Derived rate
- ₹11,439.60 / a gate
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.3 — Providing and fixing in position collapsible steel shutters with vertical channels 20x10x2 mm and braced with flat iron diagonals 20x5 mm size, with top and bottom rail of T-iron 40x40x6 mm, with 40 mm dia steel pulleys, complete with bolts, nuts, locking arrangement, stoppers, handles, including applying a priming coat of approved steel primer — is derived from 14 priced inputs for a gate and works out to ₹11,439.60 per a gate after water charges, GST, CPOH and cess. The full build-up is below.
- 3.6sqm.
- M.S. channels 18 Nos. on both sides
- 20x10x2mm @ 0.56kg/m
- 2x18x2.4 = 86.40m+
- Total = 95.04m
- 95.04m@0.56kg/m =53.22kg=0.53q
- M.S. Tee-40x40x6mm
- for bottom-1.570m+
- for top = 1.725m
- Total =3.295m Say 3.3m
- 3.3m @ 3.5kg/m = 11.55kg+
- Total = 12.705Kg. Say 0.13q
- 20mmx5mm flat iron diagonals 4 Nos.
- 4x32x0.5334 = 68.275m
- 68.275m @ 0.8kg/m = 54.62kg+
- Total = 60.08kg = 0.60q
- Priming coatChannel - 36x0.076x2.4 = 6.57sqm.+
- Tee-0.16x3.3 = 0.53sqm.+
- Flats-0.05x68 = 3.40sqm.
- Total = 10.50sqm.
- Add wastage @ 10% = 8.64m
- Add wastage @ 10% = 1.155 Kg.
- Add wastage @10% = 5.46kg
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1007 | Structurals such as tees,angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joistsMaterial | quintal | 0.53 | 5,965.00 | 3,161.45 |
| 1007 | Structurals such as tees,angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joistsMaterial | quintal | 0.13 | 5,965.00 | 775.45 |
| 1008 | Flats upto 10 mm in thicknessFlats up to 10 mm in thicknessMaterial | quintal | 0.6 | 5,450.00 | 3,270.00 |
| 9999 | Cost of rivets fixing hooks and washersMaterial | L.S. | 269.1 | 2.27 | 610.86 |
| 9999 | Cost of locking arrangements and handlesMaterial | L.S. | 67.34 | 2.27 | 152.86 |
| 4013 | Pully 40 mm diaPulley 40 mm diaMaterial | each | 10 | 40.00 | 400.00 |
| Rate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3Sub-analysis | sqm | 10.5 | 67.40 | 707.70 | |
| 0116 | Fitter (grade 1)Labour | day | 3 | 897.00 | 2,691.00 |
| 0102 | Blacksmith 1st classLabour | day | 6 | 897.00 | 5,382.00 |
| 0103 | Blacksmith 2nd classLabour | day | 6 | 816.00 | 4,896.00 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.5 | 897.00 | 448.50 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.5 | 816.00 | 408.00 |
| 0114 | BeldarLabour | day | 8 | 736.00 | 5,888.00 |
| 9999 | SundriesMaterial | L.S. | 161.46 | 2.27 | 366.51 |
- TOTAL
- 29,158.33
- Add 1 % Water charges on “W-A”
- 284.51
- TOTAL
- 29,442.84
- Add GST on “X-A” (multiplying factor 0.2127)
- 6,111.96
- TOTAL
- 35,554.80
- Add 15% CPOH on “Y-A”
- 5,227.07
- TOTAL
- 40,781.87
- Add Cess @ 1% on “Z-A”
- 400.74
- Cost of 3.6sqm.
- 41,182.61
- Cost per sqm.
- 11,439.61
- Say
- 11,439.60
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 715. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.