CPWD Analysis of Rates · Steel Work

Providing and fixing angle iron frames for doors, windows and ventilators of mild steel Angle sections of size 35x35x5 mm, joints mitred and welded by angle iron 35x35x5 mm or 35x 5 mm flat pieces to the existing T-iron frame or to the wall with dash fastener, including fixing of necessary butt hinges and screws and applying a priming coat of approved steel primer, all complete as per the direction of Engineer-In-charge

Item number
10.31
Analysis basis
Details of cost for 17.50 kg
Priced inputs
11
Derived rate
130.50 / kg

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.31 Providing and fixing angle iron frames for doors, windows and ventilators of mild steel Angle sections of size 35x35x5 mm, joints mitred and welded by angle iron 35x35x5 mm or 35x 5 mm flat pieces to the existing T-iron frame or to the wall with dash fastener, including fixing of necessary butt hinges and screws and applying a priming coat of approved steel primer, all complete as per the direction of Engineer-In-charge — is derived from 11 priced inputs for 17.50 kg and works out to ₹130.50 per kg after water charges, GST, CPOH and cess. The full build-up is below.

  • Angle/Tee iron 40x40x6 mm= 2+2+1 = 5 m
  • 5 Meters @3.5 Kg/m = 17.5 Kg+ Add
  • Wastage @5% =0.87Kg.“Total =18.37 Kg.
  • Say 0.18 Quintal
  • Add wastage @5% = 0.018 Kg Total=
CodeInputUnitQuantityRate (INR)Amount (INR)
1007Structural steel such as tees, angles, channels and R.S. JoistsStructural steel such as tees, angles channels and R.S. joistsMaterialquintal0.185,965.001,073.70
1008M.S. Flats 3x5 mm for fixing frame 6x0.05= 0.3 Metre @1.18 Kg/m= 0.354 KgFlats up to 10 mm in thicknessMaterialNaNNaNNaN
0.37Kg. Say 0.004 QunitalOtherquintal0.0045,450.0021.80
1002M.S. Bars 10mm =1x1 m = 1.00 metre @0.60Kg/m =0.60Kg + Add wastage @5% = 0.03 Kg. Total =0.63 Kg, say 0.006 Quintal Mild steel round bars 10mm dia and belowMild steel round bar 12 mm dia and belowMaterialquintal0.0065,550.0033.30
9999For applying steel primerMaterialL.S.17.942.2740.72
9999Carriage of materialMaterialL.S.5.332.2712.10
1215Welding by electric plantMaterialcm162.5040.00
0103Blacksmith 2nd ClassLabourday0.1816.0081.60
0116Fitter (Grade-I)Fitter (grade 1)Labourday0.15897.00134.55
0114BeldarLabourday0.2736.00147.20
9999SundriesMaterialL.S.8.972.2720.36
TOTAL
1,605.33
Add 1 % Water charges on “W”
16.05
TOTAL
1,621.38
Add GST on “X” (multiplying factor 0.2127)
344.87
TOTAL
1,966.25
Add 15% CPOH on “Y”
294.94
TOTAL
2,261.19
Add Cess @ 1% on “Z”
22.61
Cost for 17.50 kg
2,283.80
Rate per kg
130.50
Say
130.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 751. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.