Providing & fixing glass panes with putty and glazing clips in steel doors, windows, clerestory windows, all complete with
- Item number
- 10.30.2
- Analysis basis
- 10 glass
- Priced inputs
- 4
- Derived rate
- ₹1,390.15/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.30.2 (Providing & fixing glass panes with putty and glazing clips in steel doors, windows, clerestory windows, all complete with : 5.5 mm thick glass panes) is derived from 4 priced inputs for 10 glass and works out to ₹1,390.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- each pane = 0.10 sqm)
- Area of glass panes =1.00 sqm +
- Total =1.10 sqm
- Add wastage @ 10% = 0.10
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 2407 | MAT | Float glass sheet of nominal thickness 5.5 mm.(weight not less than 13.50 kg/sqm)Float glass panes of nominal thickness 5 mm (weight not less than 12.50 kg/sqm) | sqm | 1.1 | 529.00 | 581.90 |
| 9977 | MAT | Carriage | L.S. | 1.82 | 2.27 | 4.13 |
| 0119 | LAB | Glazier | day | 0.13 | 816.00 | 106.08 |
| 9999 | MAT | Sundries, putty, glazing clips, scaffolding etc | L.S. | 125.58 | 2.27 | 285.07 |
- TOTAL
- 977.18
- Add 1 % Water charges on “W”
- +9.77
- TOTAL
- 986.95
- Add GST on “X” (multiplying factor 0.2127)
- +209.92
- TOTAL
- 1,196.87
- Add 15% CPOH on “Y”
- +179.53
- TOTAL
- 1,376.40
- Add Cess @ 1% on “Z”
- +13.76
- Cost of 1.0 sqm
- 1,390.16
- SAY
- ₹1,390.15
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 751
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 751. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.