CPWD Analysis of Rates · Steel Work
Providing & fixing fly proof wire gauze to windows, clerestory windows & doors with M.S. Flat 15x3 mm and nuts & bolts complete
Stainless steel (grade 304) wire gauze of 0.5 mm dia wire and 1.4 mm aperture on both sides
- Item number
- 10.29.2
- Analysis basis
- Details of cost for 10 Nos. window shutter
- Priced inputs
- 8
- Derived rate
- ₹1,133.55 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.29.2 — Providing & fixing fly proof wire gauze to windows, clerestory windows & doors with M.S. Flat 15x3 mm and nuts & bolts complete Stainless steel (grade 304) wire gauze of 0.5 mm dia wire and 1.4 mm aperture on both sides — is derived from 8 priced inputs for 10 Nos and works out to ₹1,133.55 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 10x1.40x1.10=15.4 sqm
- Wire gauze 10x1.40x1.10=15.4 sqm
- Total=16.9 sqm
- M.S. Flat 15x3=10x2x(1.40+1.10)=50 metre
- Total=52.5 m
- 52.5@0.35kg/m=18.4 kg
- Add wastage @ 10 %=1.5 sqm
- Add wastage @ 5%=2.5 m
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8737 | Stainless steel wire guage (Grade-304) aperture 1.4mm and 0.50 mm dia wireStainless steel wire guage (Grade-304) aperture 1.4 mm and 0.50 mm dia wireMaterial | sqm | 16.9 | 445.00 | 7,520.50 |
| 9977 | CarriageMaterial | L.S. | 18.2 | 2.27 | 41.31 |
| 1008 | Flats upto 10 mm in thicknessFlats up to 10 mm in thicknessMaterial | quintal | 0.184 | 5,450.00 | 1,002.80 |
| 9977 | CarriageMaterial | L.S. | 18.2 | 2.27 | 41.31 |
| 0103 | Blacksmith 2nd classLabour | day | 1.7 | 816.00 | 1,387.20 |
| 0112 | Carpenter 2nd classLabour | day | 1.7 | 816.00 | 1,387.20 |
| 0114 | BeldarLabour | day | 0.6 | 736.00 | 441.60 |
| 9999 | SundriesMaterial | L.S. | 197.6 | 2.27 | 448.55 |
- TOTAL
- 12,270.47
- Add 1 % Water charges on “W”
- 122.70
- TOTAL
- 12,393.17
- Add GST on “X” (multiplying factor 0.2127)
- 2,636.03
- TOTAL
- 15,029.20
- Add 15% CPOH on “Y”
- 2,254.38
- TOTAL
- 17,283.58
- Add Cess @ 1% on “Z”
- 172.84
- Cost of 15.4 sqm.
- 17,456.42
- Cost of 1 sqm.
- 1,133.53
- Say
- 1,133.55
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 750. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works