CPWD Analysis of Rates · Steel Work
Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners , stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in-charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.)
- Item number
- 10.28
- Analysis basis
- Details of cost for 2kg
- Priced inputs
- 8
- Derived rate
- ₹772.40 / kg
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.28 — Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners , stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in-charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) — is derived from 8 priced inputs and works out to ₹772.40 per kg after water charges, GST, CPOH and cess. The full build-up is below.
- Qty= 2kg +
- Total = 2.1 kg
- for fabrication, assembling, errection, welding, curvaturing, grinding, buffling etc.
- Add wastage @ 5% = 0.10
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 4001 | Stainless steel (Grade-304)hollow section round/square tubesMaterial | kg | 2.1 | 280.00 | 588.00 |
| 4002 | Stainless steel bolts/square bar and platesMaterial | kg | 1 | 150.00 | 150.00 |
| 0102 | Blacksmith 1st classLabour | day | 0.06 | 897.00 | 53.82 |
| 0114 | BeldarLabour | day | 0.2 | 736.00 | 147.20 |
| 0100 | BandhaniLabour | day | 0.02 | 816.00 | 16.32 |
| 9999 | Welding of stainless steel sectionMaterial | L.S. | 30 | 2.27 | 68.10 |
| 9999 | Curvaturing, grinding, finishing, buffingMaterial | L.S. | 20 | 2.27 | 45.40 |
| 9999 | Sundries for making good wall and floorsMaterial | L.S. | 7.5 | 2.27 | 17.03 |
- TOTAL
- 1,085.87
- Add 1 % Water charges on “W”
- 10.86
- TOTAL
- 1,096.73
- Add GST on “X” (multiplying factor 0.2127)
- 233.27
- TOTAL
- 1,330.00
- Add 15% CPOH on “Y”
- 199.50
- TOTAL
- 1,529.50
- Add Cess @ 1% on “Z”
- 15.30
- Cost of 2 kg
- 1,544.80
- Cost of 1 kg.
- 772.40
- Say
- 772.40
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 748. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.