Providing and fixing hand rail of approved size by welding etc. to steel ladder railing, balcony railing, staircase railing and similar works, including applying priming coat of approved steel primer

G.I. pipes

Item number
10.26.3
Analysis basis
Details of cost for hand rail of railing of two
Priced inputs
7
Derived rate
203.05 / hand rail

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.26.3 Providing and fixing hand rail of approved size by welding etc. to steel ladder railing, balcony railing, staircase railing and similar works, including applying priming coat of approved steel primer G.I. pipes — is derived from 7 priced inputs for hand rail and works out to ₹203.05 per hand rail after water charges, GST, CPOH and cess. The full build-up is below.

  • flights of staircase, length of hand rail =
  • 5.40m i.e. 20.09 kg
  • G.I. pipe 40mm nominal bore = 5.40m
  • Total = 5.67m
  • Priming coat 40mm dia.Tube
  • 5.4x22/7x0.0483 = 0.82 sqm
  • (joints of hand rail and ballustards)
  • 18x4x1.00 = 72cm
  • Labour for cutting assembling & erection
  • Add wastage @ 5% = 0.27m
CodeInputUnitQuantityRate (INR)Amount (INR)
1549G.I. pipes 40 mm diaMaterialmetre5.67290.001,644.30
Rate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3Sub-analysissqm0.8267.4055.27
1215Welding by electric plantMaterialcm722.50180.00
0102Blacksmith 1st classLabourday0.24897.00215.28
0114BeldarLabourday0.9736.00662.40
0100BandhaniLabourday0.12816.0097.92
9999SundriesMaterialL.S.12.482.2728.33
TOTAL
2,883.50
Add 1 % Water charges on “W-A”
28.28
TOTAL
2,911.78
Add GST on “X-A” (multiplying factor 0.2127)
607.58
TOTAL
3,519.36
Add 15% CPOH on “Y-A”
519.61
TOTAL
4,038.97
Add Cess @ 1% on “Z-A”
39.84
Cost of 20.09 Kg.
4,078.81
Cost per 1 kg.
203.03
Say
203.05

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 745. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.