CPWD Analysis of Rates · Steel Work

Providing and fixing hand rail of approved size by welding etc. to steel ladder railing, balcony railing, staircase railing and similar works, including applying priming coat of approved steel primer

E.R.W. tubes

Item number
10.26.2
Analysis basis
Details of cost for hand rail of railing of
Priced inputs
7
Derived rate
205.75 / hand rail

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.26.2 Providing and fixing hand rail of approved size by welding etc. to steel ladder railing, balcony railing, staircase railing and similar works, including applying priming coat of approved steel primer E.R.W. tubes — is derived from 7 priced inputs for hand rail and works out to ₹205.75 per hand rail after water charges, GST, CPOH and cess. The full build-up is below.

  • two flights of staircase, length of hand rail
  • =5.40m
  • E.R.W. tube 40mm nominal bore = 5.40m
  • @ 3.28kg/m= 17.71kg
  • Total = 18.59 kg
  • Priming coat 40mm dia.Tube
  • 5.4x22/7x0.0483 = 0.82 sqm
  • (joints of hand rail and ballustards)
  • 18x4x1.00 = 72cm
  • Labour for cutting assembling & erection
  • Add wastage @ 5% = 0.88 kg
CodeInputUnitQuantityRate (INR)Amount (INR)
4011Mild steel tubes electric resistant or induction butt weldedMaterialgram18.5972.001,338.48
Rate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3Sub-analysissqm0.8267.4055.27
1215Welding by electric plantMaterialcm722.50180.00
0102Blacksmith 1st classLabourday0.24897.00215.28
0114BeldarLabourday0.9736.00662.40
0100BandhaniLabourday0.12816.0097.92
9999SundriesMaterialL.S.12.482.2728.33
TOTAL
2,577.68
Add 1 % Water charges on “W-A”
25.22
TOTAL
2,602.90
Add GST on “X-A” (multiplying factor 0.2127)
541.88
TOTAL
3,144.78
Add 15% CPOH on “Y-A”
463.43
TOTAL
3,608.21
Add Cess @ 1% on “Z-A”
35.53
Cost of 17.71 Kg.
3,643.74
Cost per 1 kg.
205.74
Say
205.75

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 744. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.