Fixing with 15x3 mm lugs 10 cm long embedded in cement concrete block 15x10x10 cm of C.C
- Item number
- 10.15.2
- Analysis basis
- Details of cost for 7.13Kg.
- Priced inputs
- 10
- Derived rate
- ₹181.25
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.15.2 (Fixing with 15x3 mm lugs 10 cm long embedded in cement concrete block 15x10x10 cm of C.C Fixing with carbon steel galvanised dash fastener of required dia and size (to be paid for separately)) is derived from 10 priced inputs and works out to ₹181.25 after water charges, GST, CPOH and cess. The full build-up is below.
- L- section - 32x22x28mm 1.60mm thick
- 2.00+2.00+1.00 = 5.00 m
- Width of MS sheet = 32+24.80+22+24.80+
- 10mm = 113.60mm = 0.1136 m
- Area of MS sheet = 0.1136x5.00x0.0016 =
- 0.0009088 sqm
- Weight of Sheet = 0.0009088x7850 =7.134
- kg
- Total = 7.491 kg Say 7.49 kg
- M.S. bars 10mm = 1x1m = 1 metre
- 1 metre @ 0.60kg/m = 0.60Kg.
- Total = 0.63 Kg. Say = 0.006 qunital
- Add wastage @ 5% = 0.357Kg.
- Add wastage @ 5% = 0.03Kg.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 4011 | MAT | Mild steel tubes electric resistant or induction butt welded | gram | 7.49 | 72.00 | 539.28 |
| 1002 | MAT | Mild steel round bar 12 mm dia and below | quintal | 0.006 | 5,550.00 | 33.30 |
| 0595 | MAT | Bright finished or black enamelled mild steel butt hinges 100x58x1.90 mmBright finished or black enameled ISI marked IS:1341 mild steel pressed butt hinges 100x58x 1.90 mm | 10 Nos | 0.6 | 80.00 | 48.00 |
| 9999 | MAT | For screws and nuts and bolts | L.S. | 35.88 | 2.27 | 81.45 |
| 9999 | MAT | For applying steel primer | L.S. | 17.94 | 2.27 | 40.72 |
| 9977 | MAT | Carriage of material | L.S. | 5.33 | 2.27 | 12.10 |
| 0103 | LAB | Blacksmith 2nd class | day | 0.04 | 816.00 | 32.64 |
| 0116 | LAB | Fitter (grade 1) | day | 0.06 | 897.00 | 53.82 |
| 0114 | LAB | Beldar | day | 0.08 | 736.00 | 58.88 |
| 9999 | MAT | Sundries | L.S. | 3.64 | 2.27 | 8.26 |
- TOTAL
- 908.45
- Add 1 % Water charges on “W”
- +9.08
- TOTAL
- 917.53
- Add GST on “X” (multiplying factor 0.2127)
- +195.16
- TOTAL
- 1,112.69
- Add 15% CPOH on “Y”
- +166.90
- TOTAL
- 1,279.59
- Add Cess @ 1% on “Z”
- +12.80
- Cost for 7.13Kg.
- 1,292.39
- Cost for 1 Kg.
- 181.26
- SAY
- ₹181.25
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 735
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 735. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.