Fixing with 15x3 mm lugs 10 cm long embedded in cement concrete block 15x10x10 cm of C.C

1:3:6 (1 Cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
Item number
10.15.1
Analysis basis
Details of cost for 7.13Kg.
Priced inputs
12
Derived rate
₹195.20
D-01/RATE ANALYSISITEM 10.15.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.15.1 (Fixing with 15x3 mm lugs 10 cm long embedded in cement concrete block 15x10x10 cm of C.C 1:3:6 (1 Cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)) is derived from 12 priced inputs and works out to ₹195.20 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • L- section - 32x22x28mm 1.60mm thick
  • 2.00+2.00+1.00 = 5.00 m
  • Width of MS sheet = 32+24.80+22+
  • 24.80+10mm = 113.60mm = 0.1136 m
  • Area of MS sheet = 0.1136x5.00x0.0016 =
  • 0.0009088 sqm
  • Weight of Sheet = 0.0009088x7850 =7.134
  • kg
  • Total = 7.491 kg Say 7.49 kg
  • M.S. bars 10mm = 1x1m = 1 metre
  • 1 metre @ 0.60kg/m = 0.60Kg.
  • Total = 0.63 Kg. Say = 0.006 qunital
  • M.S. flat 15x3mm = 6x10cm = 0.60 metre
  • 0.6 metre @ 0.35kg/m = 0.21Kg
  • Total = 0.22 kg = 0.002q
  • Cement concrete block 1:3:6- 6x15x10x10cm= 0.009 cum
  • Add wastage @ 5% = 0.357Kg.
  • Add wastage @ 5% = 0.03Kg.
  • Add wastage @ 5% = 0.01 Kg.
ANALYSIS OF RATES · ITEM 10.15.1DETAILS OF COST FOR 7.13KG
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
4011MATMild steel tubes electric resistant or induction butt weldedgram7.4972.00539.28
1002MATMild steel round bar 12 mm dia and belowquintal0.0065,550.0033.30
1008MATFlats upto 10 mm in thicknessFlats up to 10 mm in thicknessquintal0.0025,450.0010.90
SUBRate as per item no 4.2.5 of SH : Concrete workRate as per item 4.2.5cum0.0099,311.4083.80
0595MATBright finished or black enamelled mild steel butt hinges 100x58x1.90 mmBright finished or black enameled ISI marked IS:1341 mild steel pressed butt hinges 100x58x 1.90 mm10 Nos0.680.0048.00
9999MATFor screws and nuts and boltsL.S.35.882.2781.45
9999MATFor applying steel primerL.S.17.942.2740.72
9977MATCarriage of materialL.S.5.332.2712.10
0103LABBlacksmith 2nd classday0.04816.0032.64
0116LABFitter (grade 1)day0.06897.0053.82
0114LABBeldarday0.08736.0058.88
9999MATSundriesL.S.3.642.278.26
BUILD-UP TO RATE
TOTAL
1,003.15
Add 1 % Water charges on “W-A”
+9.19
TOTAL
1,012.34
Add GST on “X-A” (multiplying factor 0.2127)
+197.50
TOTAL
1,209.84
Add 15% CPOH on “Y-A”
+168.91
TOTAL
1,378.75
Add Cess @ 1% on “Z-A”
+12.95
Cost for 7.13Kg.
1,391.70
Cost for 1 Kg.
195.19
SAY
₹195.20
D-02/SOURCEPRINTED PAGE 734
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
734

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 734. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSTEEL WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.