R/DAR 2023

Fixing with 15x3 mm lugs 10 cm long embedded in cement concrete block 15x10x10 cm of C.C

1:3:6 (1 Cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
Item number
10.11.1
Analysis basis
10 Nos
Priced inputs
13
Derived rate
₹131.05/ KG
D-01/RATE ANALYSISITEM 10.11.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.11.1 (Fixing with 15x3 mm lugs 10 cm long embedded in cement concrete block 15x10x10 cm of C.C 1:3:6 (1 Cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)) is derived from 13 priced inputs for 10 Nos and works out to ₹131.05 per kg after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • door of size 2.075x1.175m = 2.44 sqm.
  • (weight10x 30=300 kg).
  • Labour for fabrication
  • Fixing with CC 1:3:6 blocks, wooden plugs
  • and screws or rawl plugs and screws or
  • with fixing clips and bolts and nuts as
  • required
  • Cement concrete blocks 15x10x10cm
  • =10x6x0.15x0.10x0.10= 0.09 cum
  • Labour for fixing for 10 Nos.door/window
  • Apply steel primer (10x2.44x1.00 for both
  • sides)=24.40 sqm
ANALYSIS OF RATES · ITEM 10.11.1DETAILS OF COST FOR 10 NOS. DOUBLE LEAF
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1011MATSteel glazed door,window/ ventilator, all members like as F7D, F4B, K11 and K12B etcSteel glazed door, window/ ventilator, all members viz. F7D, F4B, K11 and K12B etc.kg30059.0017,700.00
9977MATCarriage of Steel DoorL.S.403.72.27916.40
0103LABBlacksmith 2nd classday1.7816.001,387.20
0116LABFitter (grade 1)day2.6897.002,332.20
0114LABBeldarday3.4736.002,502.40
9999MATSundriesL.S.153.72.27348.90
SUBRate as per item no 4.2.5 of SH : Concrete workRate as per item 4.2.5cum0.099,311.40838.03
0114LABBeldarday0.27736.00198.72
0115LABCollieCoolieday0.195736.00143.52
0130LABMistryday0.084897.0075.35
0128LABMateday0.012816.009.79
9999MATHire charges of machine, scaffolding and sundriesL.S.122.22.27277.39
SUBRate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3sqm24.467.401,644.56
BUILD-UP TO RATE
TOTAL
28,374.46
Add 1 % Water charges on “W-A”
+258.92
TOTAL
28,633.38
Add GST on “X-A” (multiplying factor 0.2127)
+5,562.27
TOTAL
34,195.65
Add 15% CPOH on “Y-A”
+4,756.96
TOTAL
38,952.61
Add Cess @ 1% on “Z-A”
+364.70
Cost for 300 kg.
39,317.31
Cost of 1 kg.
131.06
SAY
₹131.05
D-02/SOURCEPRINTED PAGE 725
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
725

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 725. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.