CPWD Analysis of Rates · Steel Work
Fixing with 15x3 mm lugs 10 cm long embedded in cement concrete block 15x10x10 cm of C.C
1:3:6 (1 Cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
- Item number
- 10.11.1
- Analysis basis
- Details of cost for 10 Nos. double leaf
- Priced inputs
- 13
- Derived rate
- ₹131.05 / kg
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.11.1 — Fixing with 15x3 mm lugs 10 cm long embedded in cement concrete block 15x10x10 cm of C.C 1:3:6 (1 Cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) — is derived from 13 priced inputs for 10 Nos and works out to ₹131.05 per kg after water charges, GST, CPOH and cess. The full build-up is below.
- door of size 2.075x1.175m = 2.44 sqm.
- (weight10x 30=300 kg).
- Labour for fabrication
- Fixing with CC 1:3:6 blocks, wooden plugs
- and screws or rawl plugs and screws or
- with fixing clips and bolts and nuts as
- required
- Cement concrete blocks 15x10x10cm
- =10x6x0.15x0.10x0.10= 0.09 cum
- Labour for fixing for 10 Nos.door/window
- Apply steel primer (10x2.44x1.00 for both
- sides)=24.40 sqm
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1011 | Steel glazed door,window/ ventilator, all members like as F7D, F4B, K11 and K12B etcSteel glazed door, window/ ventilator, all members viz. F7D, F4B, K11 and K12B etc.Material | kg | 300 | 59.00 | 17,700.00 |
| 9977 | Carriage of Steel DoorMaterial | L.S. | 403.7 | 2.27 | 916.40 |
| 0103 | Blacksmith 2nd classLabour | day | 1.7 | 816.00 | 1,387.20 |
| 0116 | Fitter (grade 1)Labour | day | 2.6 | 897.00 | 2,332.20 |
| 0114 | BeldarLabour | day | 3.4 | 736.00 | 2,502.40 |
| 9999 | SundriesMaterial | L.S. | 153.7 | 2.27 | 348.90 |
| Rate as per item no 4.2.5 of SH : Concrete workRate as per item 4.2.5Sub-analysis | cum | 0.09 | 9,311.40 | 838.03 | |
| 0114 | BeldarLabour | day | 0.27 | 736.00 | 198.72 |
| 0115 | CollieCoolieLabour | day | 0.195 | 736.00 | 143.52 |
| 0130 | MistryLabour | day | 0.084 | 897.00 | 75.35 |
| 0128 | MateLabour | day | 0.012 | 816.00 | 9.79 |
| 9999 | Hire charges of machine, scaffolding and sundriesMaterial | L.S. | 122.2 | 2.27 | 277.39 |
| Rate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3Sub-analysis | sqm | 24.4 | 67.40 | 1,644.56 |
- TOTAL
- 28,374.46
- Add 1 % Water charges on “W-A”
- 258.92
- TOTAL
- 28,633.38
- Add GST on “X-A” (multiplying factor 0.2127)
- 5,562.27
- TOTAL
- 34,195.65
- Add 15% CPOH on “Y-A”
- 4,756.96
- TOTAL
- 38,952.61
- Add Cess @ 1% on “Z-A”
- 364.70
- Cost for 300 kg.
- 39,317.31
- Cost of 1 kg.
- 131.06
- Say
- 131.05
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 725. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.