Fixing with 15x3 mm lugs 10 cm long embedded in cement concrete block 15x10x10 cm of C.C
- Item number
- 10.10.1
- Analysis basis
- one door
- Priced inputs
- 6
- Derived rate
- ₹82.45/ ONE DOOR
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.10.1 (Fixing with 15x3 mm lugs 10 cm long embedded in cement concrete block 15x10x10 cm of C.C 1:3:6 (1 Cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)) is derived from 6 priced inputs for one door and works out to ₹82.45 per one door after water charges, GST, CPOH and cess. The full build-up is below.
- 1.52sqm.(weight 15 kg)
- Cement concrete blocks 15x10x10cm
- =6x0.15x0.10x0.10= 0.009 cum
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per item no 4.2.5 of SH : Concrete workRate as per item 4.2.5 | cum | 0.009 | 9,311.40 | 83.80 | |
| 0102 | LAB | Blacksmith 1st class | day | 0.17 | 897.00 | 152.49 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.08 | 897.00 | 71.76 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.08 | 816.00 | 65.28 |
| 0114 | LAB | Beldar | day | 0.5 | 736.00 | 368.00 |
| 9977 | MAT | Sundries for carriage of material | L.S. | 67.28 | 2.27 | 152.73 |
- TOTAL
- 894.06
- Add 1 % Water charges on “W-A”
- +8.10
- TOTAL
- 902.16
- Add GST on “X-A” (multiplying factor 0.2127)
- +174.07
- TOTAL
- 1,076.23
- Add 15% CPOH on “Y-A”
- +148.86
- TOTAL
- 1,225.09
- Add Cess @ 1% on “Z-A”
- +11.41
- Cost of 15 kg
- 1,236.50
- Cost per kg
- 82.43
- SAY
- ₹82.45
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 724
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 724. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.