Fixing with 15x3 mm lugs 10 cm long embedded in cement concrete block 15x10x10 cm of C.C

1:3:6 (1 Cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
Item number
10.10.1
Analysis basis
one door
Priced inputs
6
Derived rate
₹82.45/ ONE DOOR
D-01/RATE ANALYSISITEM 10.10.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.10.1 (Fixing with 15x3 mm lugs 10 cm long embedded in cement concrete block 15x10x10 cm of C.C 1:3:6 (1 Cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)) is derived from 6 priced inputs for one door and works out to ₹82.45 per one door after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 1.52sqm.(weight 15 kg)
  • Cement concrete blocks 15x10x10cm
  • =6x0.15x0.10x0.10= 0.009 cum
ANALYSIS OF RATES · ITEM 10.10.1DETAILS OF COST FOR ONE DOOR 2X0.76M =
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no 4.2.5 of SH : Concrete workRate as per item 4.2.5cum0.0099,311.4083.80
0102LABBlacksmith 1st classday0.17897.00152.49
0123LABMason 1st classMason 1st classday0.08897.0071.76
0124LABMason 2nd classMason 2nd classday0.08816.0065.28
0114LABBeldarday0.5736.00368.00
9977MATSundries for carriage of materialL.S.67.282.27152.73
BUILD-UP TO RATE
TOTAL
894.06
Add 1 % Water charges on “W-A”
+8.10
TOTAL
902.16
Add GST on “X-A” (multiplying factor 0.2127)
+174.07
TOTAL
1,076.23
Add 15% CPOH on “Y-A”
+148.86
TOTAL
1,225.09
Add Cess @ 1% on “Z-A”
+11.41
Cost of 15 kg
1,236.50
Cost per kg
82.43
SAY
₹82.45
D-02/SOURCEPRINTED PAGE 724
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
724

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 724. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.