CPWD Analysis of Rates · Sanitary Installations
Providing and fixing PTMT towel rail complete with brackets fixed to wooden cleats with CP brass screws with concealed fittings arrangement of approved quality and colour
450 mm long towel rail with total length of 495 mm, 78 mm wide and effective height of 88 mm, weighing not less than 170 gms
- Item number
- 17.73.1
- Analysis basis
- Details of cost for one no.
- Priced inputs
- 6
- Derived rate
- ₹673.40 / one no
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.73.1 — Providing and fixing PTMT towel rail complete with brackets fixed to wooden cleats with CP brass screws with concealed fittings arrangement of approved quality and colour 450 mm long towel rail with total length of 495 mm, 78 mm wide and effective height of 88 mm, weighing not less than 170 gms — is derived from 6 priced inputs for one no and works out to ₹673.40 per one no after water charges, GST, CPOH and cess. The full build-up is below.
- Wooden cleates
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7505 | PTMT Towel Rail (450mm)PTMT - Towel Rail (450 mm long )Material | each | 1 | 132.00 | 132.00 |
| Rate as per item no 8.23 of SH : Cladding workRate as per item 8.23Sub-analysis | each | 2 | 40.85 | 81.70 | |
| 0588 | Chromium plated Brass screws 25 mmMaterial | 100 Nos | 0.06 | 177.00 | 10.62 |
| 9977 | Carriage of materialsMaterial | L.S. | 4.16 | 2.27 | 9.44 |
| 0112 | Carpenter 2nd classLabour | day | 0.17 | 816.00 | 138.72 |
| 0114 | BeldarLabour | day | 0.17 | 736.00 | 125.12 |
- TOTAL
- 497.60
- Add 1 % Water charges on “W-A”
- 4.16
- TOTAL
- 501.76
- Add GST on “X-A” (multiplying factor 0.2127)
- 89.35
- TOTAL
- 591.11
- Add 15% CPOH on “Y-A”
- 76.41
- TOTAL
- 667.52
- Add Cess @ 1% on “Z-A”
- 5.86
- Cost of each
- 673.38
- Say
- 673.40
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1384. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.