Providing and fixing PTMT towel ring trapezoidal shape 215 mm long, 200 mm wide with minimum distances of 37 mm from wall face with concealed fittings arrangement of approved quality and colour, weighing not less than 88 gms

Item number
17.72
Priced inputs
2
Derived rate
₹231.95
D-01/RATE ANALYSISITEM 17.72

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.72 (Providing and fixing PTMT towel ring trapezoidal shape 215 mm long, 200 mm wide with minimum distances of 37 mm from wall face with concealed fittings arrangement of approved quality and colour, weighing not less than 88 gms) is derived from 2 priced inputs and works out to ₹231.95 after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 17.72
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7504MATPTMT - Towel Ring 215x200x37mmPTMT - Towel Ring 215x200x37 mmeach1117.00117.00
9988MATCarriage of materials and fixing chargesL.S.20.282.2746.04
BUILD-UP TO RATE
TOTAL
163.04
Add 1 % Water charges on “W”
+1.63
TOTAL
164.67
Add GST on “X” (multiplying factor 0.2127)
+35.03
TOTAL
199.70
Add 15% CPOH on “Y”
+29.96
TOTAL
229.66
Add Cess @ 1% on “Z”
+2.30
Cost of each
231.96
SAY
₹231.95
D-02/SOURCEPRINTED PAGE 1383
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1383

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1383. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSANITARY INSTALLATIONS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.