Providing and fixing PTMT Waste Coupling for wash basin and sink, of approved quality and colour

Waste coupling 31 mm dia of 79 mm length and 62mm breadth weighing not less than 45 gms
Item number
17.69.1
Analysis basis
one no
Priced inputs
2
Derived rate
₹115.30/ ONE NO
D-01/RATE ANALYSISITEM 17.69.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.69.1 (Providing and fixing PTMT Waste Coupling for wash basin and sink, of approved quality and colour Waste coupling 31 mm dia of 79 mm length and 62mm breadth weighing not less than 45 gms) is derived from 2 priced inputs for one no and works out to ₹115.30 per one no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 17.69.1DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7491MATPTMT Waste Coupling 31/32MMPTMT - Waste Coupling 31/32 mmeach135.0035.00
9988MATCarriage of materials and fixing chargesL.S.20.282.2746.04
BUILD-UP TO RATE
TOTAL
81.04
Add 1 % Water charges on “W”
+0.81
TOTAL
81.85
Add GST on “X” (multiplying factor 0.2127)
+17.41
TOTAL
99.26
Add 15% CPOH on “Y”
+14.89
TOTAL
114.15
Add Cess @ 1% on “Z”
+1.14
Cost of each
115.29
SAY
₹115.30
D-02/SOURCEPRINTED PAGE 1381
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1381

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1381. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.