Painting sand cast iron/ centrifugally cast (spun) iron soil, waste vent pipes and fittings with two coats of synthetic enamel paint of any colour such as chocolate grey, or buff etc. over a coat of primer (of approved quality) for new work
- Item number
- 17.65.2
- Analysis basis
- 10 metres
- Priced inputs
- 3
- Derived rate
- ₹62.95/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.65.2 (Painting sand cast iron/ centrifugally cast (spun) iron soil, waste vent pipes and fittings with two coats of synthetic enamel paint of any colour such as chocolate grey, or buff etc. over a coat of primer (of approved quality) for new work : 75 mm diameter pipe) is derived from 3 priced inputs for 10 metres and works out to ₹62.95 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Perimeter = 3.14x82 mm =257.71
- Area 10x0.2577 =2.577 sqm say 2.60 sq. m
- for outer surface
- Priming coat
- Painting two coats with paint of any colour
- such as choclate grey or buff etc.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3 | sqm | 2.6 | 67.40 | 175.24 | |
| SUB | Rate as per item no 13.61.1 of SH : FinishingRate as per item 13.61.1 | sqm | 2.6 | 155.90 | 405.34 | |
| 9999 | MAT | Add for delay | L.S. | 15.21 | 2.27 | 34.53 |
- TOTAL
- 615.11
- Add 1 % Water charges on “W-A”
- +0.35
- TOTAL
- 615.46
- Add GST on “X-A” (multiplying factor 0.2127)
- +7.42
- TOTAL
- 622.88
- Add 15% CPOH on “Y-A”
- +6.34
- TOTAL
- 629.22
- Add Cess @ 1% on “Z-A”
- +0.49
- Cost of 10 metres
- 629.71
- Cost of 1 metre
- 62.97
- SAY
- ₹62.95
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1378
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1378. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.