Re-painting C.I. cistern with bitumastic or any other anti-corrosive paint inside and white paint on the outside surface of the cistern, flush pipe, other fittings, etc. complete, including polishing of wooden seat and lid and cleaning of W.C. pan with acid wherever necessary
- Item number
- 17.63
- Analysis basis
- one cistern
- Priced inputs
- 6
- Derived rate
- ₹673.70/ ONE CISTERN
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.63 (Re-painting C.I. cistern with bitumastic or any other anti-corrosive paint inside and white paint on the outside surface of the cistern, flush pipe, other fittings, etc. complete, including polishing of wooden seat and lid and cleaning of W.C. pan with acid wherever necessary) is derived from 6 priced inputs for one cistern and works out to ₹673.70 per one cistern after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0828 | MAT | Anticorrosive bituminous paint (black) | litre | 0.23 | 120.00 | 27.60 |
| 0834 | MAT | Synthetic enamel paint in all shades except black or chocolate shade | litre | 0.2 | 178.00 | 35.60 |
| 9999 | MAT | Polishing of wooden seat and cleaning of W.C. pan with acid | L.S. | 20.67 | 2.27 | 46.92 |
| 9988 | MAT | Sundries and carriage of materials | L.S. | 7.15 | 2.27 | 16.23 |
| 0131 | LAB | Painter | day | 0.2 | 816.00 | 163.20 |
| 0114 | LAB | Beldar | day | 0.25 | 736.00 | 184.00 |
- TOTAL
- 473.55
- Add 1 % Water charges on “W”
- +4.74
- TOTAL
- 478.29
- Add GST on “X” (multiplying factor 0.2127)
- +101.73
- TOTAL
- 580.02
- Add 15% CPOH on “Y”
- +87.00
- TOTAL
- 667.02
- Add Cess @ 1% on “Z”
- +6.67
- Cost of each
- 673.69
- SAY
- ₹673.70
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1377
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1377. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.