Re-painting C.I. cistern with bitumastic or any other anti-corrosive paint inside and white paint on the outside surface of the cistern, flush pipe, other fittings, etc. complete, including polishing of wooden seat and lid and cleaning of W.C. pan with acid wherever necessary

Item number
17.63
Analysis basis
one cistern
Priced inputs
6
Derived rate
₹673.70/ ONE CISTERN
D-01/RATE ANALYSISITEM 17.63

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.63 (Re-painting C.I. cistern with bitumastic or any other anti-corrosive paint inside and white paint on the outside surface of the cistern, flush pipe, other fittings, etc. complete, including polishing of wooden seat and lid and cleaning of W.C. pan with acid wherever necessary) is derived from 6 priced inputs for one cistern and works out to ₹673.70 per one cistern after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 17.63DETAILS OF COST FOR ONE CISTERN WITH FITTINGS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0828MATAnticorrosive bituminous paint (black)litre0.23120.0027.60
0834MATSynthetic enamel paint in all shades except black or chocolate shadelitre0.2178.0035.60
9999MATPolishing of wooden seat and cleaning of W.C. pan with acidL.S.20.672.2746.92
9988MATSundries and carriage of materialsL.S.7.152.2716.23
0131LABPainterday0.2816.00163.20
0114LABBeldarday0.25736.00184.00
BUILD-UP TO RATE
TOTAL
473.55
Add 1 % Water charges on “W”
+4.74
TOTAL
478.29
Add GST on “X” (multiplying factor 0.2127)
+101.73
TOTAL
580.02
Add 15% CPOH on “Y”
+87.00
TOTAL
667.02
Add Cess @ 1% on “Z”
+6.67
Cost of each
673.69
SAY
₹673.70
D-02/SOURCEPRINTED PAGE 1377
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1377

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1377. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.