Painting C.I. cistern with bitumastic or any other anti-corrosive paint inside and white paint over a coat of zinc chromate yellow primer (of approved quality ) on the outside surface of the cistern, flush pipe, other fittings, etc. complete for new work

Item number
17.62
Analysis basis
Details of cost for one cistern with fittings
Priced inputs
7
Derived rate
1,020.60 / one cistern

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.62 Painting C.I. cistern with bitumastic or any other anti-corrosive paint inside and white paint over a coat of zinc chromate yellow primer (of approved quality ) on the outside surface of the cistern, flush pipe, other fittings, etc. complete for new work — is derived from 7 priced inputs for one cistern and works out to ₹1,020.60 per one cistern after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0828Anticorrosive bituminous paint (black)Materiallitre0.23120.0027.60
4202Red oxide Zinc chromate primerMateriallitre0.2140.0028.00
0834Synthetic enamel paint in all shades except black or chocolate shadeMateriallitre0.4178.0071.20
9977Carriage of materialsMaterialL.S.1.432.273.25
9999SundriesMaterialL.S.6.762.2715.35
0131PainterLabourday0.25816.00204.00
0114BeldarLabourday0.5736.00368.00
TOTAL
717.40
Add 1 % Water charges on “W”
7.17
TOTAL
724.57
Add GST on “X” (multiplying factor 0.2127)
154.12
TOTAL
878.69
Add 15% CPOH on “Y”
131.80
TOTAL
1,010.49
Add Cess @ 1% on “Z”
10.10
Cost of each
1,020.59
Say
1,020.60

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1376. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.