Providing and fixing trap of self cleansing design with screwed down or hinged grating with or without vent arm complete, including cost of cutting and making good the walls and floors : 100 mm inlet and 75 mm outlet
- Item number
- 17.60.2.2
- Analysis basis
- one no
- Priced inputs
- 5
- Derived rate
- ₹1,558.35/ ONE NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.60.2.2 (Providing and fixing trap of self cleansing design with screwed down or hinged grating with or without vent arm complete, including cost of cutting and making good the walls and floors : 100 mm inlet and 75 mm outlet Sand Cast Iron S&S as per IS1729) is derived from 5 priced inputs for one no and works out to ₹1,558.35 per one no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1898 | MAT | 100 mm S.C.I. trap with 100 mm inlet and 75 mm outlet | each | 1 | 242.00 | 242.00 |
| 9999 | MAT | Cement, sand and grit etc. | L.S. | 13.52 | 2.27 | 30.69 |
| 9977 | MAT | Carriage of materials | L.S. | 2.73 | 2.27 | 6.20 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.5 | 897.00 | 448.50 |
| 0114 | LAB | Beldar | day | 0.5 | 736.00 | 368.00 |
- TOTAL
- 1,095.39
- Add 1 % Water charges on “W”
- +10.95
- TOTAL
- 1,106.34
- Add GST on “X” (multiplying factor 0.2127)
- +235.32
- TOTAL
- 1,341.66
- Add 15% CPOH on “Y”
- +201.25
- TOTAL
- 1,542.91
- Add Cess @ 1% on “Z”
- +15.43
- Cost of each
- 1,558.34
- SAY
- ₹1,558.35
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1374
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1374. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.