CPWD Analysis of Rates · Sanitary Installations

Providing and fixing Hubless centrifugally cast iron offsets epoxy coated inside & outside as per IS:15905 65 mm offsets

With 75 mm dia pipe

Item number
17.53A.1.2
Analysis basis
Detail of cost for one no.
Priced inputs
2
Derived rate
454.50 / one no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.53A.1.2 Providing and fixing Hubless centrifugally cast iron offsets epoxy coated inside & outside as per IS:15905 65 mm offsets With 75 mm dia pipe — is derived from 2 priced inputs for one no and works out to ₹454.50 per one no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
7636Hubless centrifugally cast (spun) iron 65 mm offset with 75 mm dia pipe as per IS 15905Materialeach1295.00295.00
9977Carriage of materials and fixing chargesMaterialL.S.10.792.2724.49
TOTAL
319.49
Add 1 % Water charges on “W”
3.19
TOTAL
322.68
Add GST on “X” (multiplying factor 0.2127)
68.63
TOTAL
391.31
Add 15% CPOH on “Y”
58.70
TOTAL
450.01
Add Cess @ 1% on “Z”
4.50
Cost of each
454.51
Say
454.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1361. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.