Skip to main content

CPWD Analysis of Rates · Sanitary Installations

Providing and fixing Hubless centrifugally cast iron offsets epoxy coated inside & outside as per IS:15905 65 mm offsets

With 100 mm dia pipe

Item number
17.53A.1.1
Analysis basis
Detail of cost for one no.
Priced inputs
2
Derived rate
547.00 / one no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.53A.1.1 Providing and fixing Hubless centrifugally cast iron offsets epoxy coated inside & outside as per IS:15905 65 mm offsets With 100 mm dia pipe — is derived from 2 priced inputs for one no and works out to ₹547.00 per one no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
7635Hubless centrifugally cast (spun) iron 65 mm offset with 100 mm dia pipe as per IS 15905Materialeach1360.00360.00
9977Carriage of materials and fixing chargesMaterialL.S.10.792.2724.49
TOTAL
384.49
Add 1 % Water charges on “W”
3.84
TOTAL
388.33
Add GST on “X” (multiplying factor 0.2127)
82.60
TOTAL
470.93
Add 15% CPOH on “Y”
70.64
TOTAL
541.57
Add Cess @ 1% on “Z”
5.42
Cost of each
546.99
Say
547.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1360. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works