CPWD Analysis of Rates · Sanitary Installations

Providing and fixing double equal plain invert branch of required degree: 100x100x100x100 mm

Hubless centrifugally cast (spun) iron epoxy coated inside & outside as per IS:15905

Item number
17.49.1.3
Analysis basis
Detail of cost for one no.
Priced inputs
2
Derived rate
1,106.35 / one no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.49.1.3 Providing and fixing double equal plain invert branch of required degree: 100x100x100x100 mm Hubless centrifugally cast (spun) iron epoxy coated inside & outside as per IS:15905 — is derived from 2 priced inputs for one no and works out to ₹1,106.35 per one no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
7631Hubless centrifugally cast (spun) iron double equal plain invert branch as per IS 15905 - 100x100x100x100 mm diaMaterialeach1747.00747.00
9977Carriage of materials and fixing chargesMaterialL.S.13.522.2730.69
TOTAL
777.69
Add 1 % Water charges on “W”
7.78
TOTAL
785.47
Add GST on “X” (multiplying factor 0.2127)
167.07
TOTAL
952.54
Add 15% CPOH on “Y”
142.88
TOTAL
1,095.42
Add Cess @ 1% on “Z”
10.95
Cost of each
1,106.37
Say
1,106.35

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1352. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works