Providing and fixing double equal plain invert branch of required degree: 100x100x100x100 mm

Sand cast iron S&S as per IS 3989
Item number
17.49.1.2
Analysis basis
one no
Priced inputs
2
Derived rate
₹989.70/ ONE NO
D-01/RATE ANALYSISITEM 17.49.1.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.49.1.2 (Providing and fixing double equal plain invert branch of required degree: 100x100x100x100 mm Sand cast iron S&S as per IS 3989) is derived from 2 priced inputs for one no and works out to ₹989.70 per one no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 17.49.1.2DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
3685MATS.C.I. S&S double equal invert branch of required degree100x100x100x100 mm diaS.C.I. S&S double equal invert branch of required degree 100x100x100x100 mm diaeach1665.00665.00
9988MATCarriage of materials and fixing chargesL.S.13.522.2730.69
BUILD-UP TO RATE
TOTAL
695.69
Add 1 % Water charges on “W”
+6.96
TOTAL
702.65
Add GST on “X” (multiplying factor 0.2127)
+149.45
TOTAL
852.10
Add 15% CPOH on “Y”
+127.82
TOTAL
979.92
Add Cess @ 1% on “Z”
+9.80
Cost of each
989.72
SAY
₹989.70
D-02/SOURCEPRINTED PAGE 1352
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1352

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1352. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.