Providing and fixing single equal plain junction of required degree with access door, insertion rubber washer 3 mm thick, bolts and nuts complete 100x100x100 mm

Sand cast iron S&S as per IS - 3989
Item number
17.43.1.2
Analysis basis
one no
Priced inputs
3
Derived rate
₹925.70/ ONE NO
D-01/RATE ANALYSISITEM 17.43.1.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.43.1.2 (Providing and fixing single equal plain junction of required degree with access door, insertion rubber washer 3 mm thick, bolts and nuts complete 100x100x100 mm Sand cast iron S&S as per IS - 3989) is derived from 3 priced inputs for one no and works out to ₹925.70 per one no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 17.43.1.2DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
3644MATS.C.I. S&S single equal junctions with access door 100x100x100 mmS.C.I. S&S single equal junctions with access door 100x100x 100 mmeach1600.00600.00
1374MATRubber insertions for 100 mm dia pipe jointseach120.0020.00
9988MATCarriage of materials and fixing chargesL.S.13.522.2730.69
BUILD-UP TO RATE
TOTAL
650.69
Add 1 % Water charges on “W”
+6.51
TOTAL
657.20
Add GST on “X” (multiplying factor 0.2127)
+139.79
TOTAL
796.99
Add 15% CPOH on “Y”
+119.55
TOTAL
916.54
Add Cess @ 1% on “Z”
+9.17
Cost of each
925.71
SAY
₹925.70
D-02/SOURCEPRINTED PAGE 1344
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1344

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1344. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.