Providing and fixing single equal plain junction of required degree with access door, insertion rubber washer 3 mm thick, bolts and nuts complete 100x100x100 mm

Sand cast iron S&S as per IS - 1729

Item number
17.43.1.1
Analysis basis
Details of cost for one no.
Priced inputs
3
Derived rate
726.55 / one no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.43.1.1 Providing and fixing single equal plain junction of required degree with access door, insertion rubber washer 3 mm thick, bolts and nuts complete 100x100x100 mm Sand cast iron S&S as per IS - 1729 — is derived from 3 priced inputs for one no and works out to ₹726.55 per one no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
1631S.C.I. single equal junctions 100x100x100 mm dia with access doorMaterialeach1460.00460.00
1374Rubber insertions for 100 mm dia pipe jointsMaterialeach120.0020.00
9988Carriage of materials and fixing chargesMaterialL.S.13.522.2730.69
TOTAL
510.69
Add 1 % Water charges on “W”
5.11
TOTAL
515.80
Add GST on “X” (multiplying factor 0.2127)
109.71
TOTAL
625.51
Add 15% CPOH on “Y”
93.83
TOTAL
719.34
Add Cess @ 1% on “Z”
7.19
Cost of each
726.53
Say
726.55

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1343. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works