Providing and fixing bend of required degree with access door, insertion rubber washer 3 mm thick, bolts and nuts complete 100 mm dia

Hubless centrifugally cast (spun) iron epoxy coated inside & outside as per IS:15905
Item number
17.38.1.3
Analysis basis
one no
Priced inputs
3
Derived rate
₹567.20/ ONE NO
D-01/RATE ANALYSISITEM 17.38.1.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.38.1.3 (Providing and fixing bend of required degree with access door, insertion rubber washer 3 mm thick, bolts and nuts complete 100 mm dia Hubless centrifugally cast (spun) iron epoxy coated inside & outside as per IS:15905) is derived from 3 priced inputs for one no and works out to ₹567.20 per one no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 17.38.1.3DETAIL OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7639MATHubless centrifugally cast (spun) iron bend with access door - 100 mm dia as per IS IS:15905Hubless centrifugally cast (spun) iron bend with access door - 100 mm dia as per IS 15905each1348.00348.00
1374MATRubber insertions for 100 mm dia pipe jointseach120.0020.00
9977MATCarriage of materials and fixing chargesL.S.13.522.2730.69
BUILD-UP TO RATE
TOTAL
398.69
Add 1 % Water charges on “W”
+3.99
TOTAL
402.68
Add GST on “X” (multiplying factor 0.2127)
+85.65
TOTAL
488.33
Add 15% CPOH on “Y”
+73.25
TOTAL
561.58
Add Cess @ 1% on “Z”
+5.62
Cost of each
567.20
SAY
₹567.20
D-02/SOURCEPRINTED PAGE 1335
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1335

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1335. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.