Providing and fixing mirror of superior glass (of approved quality) and of required shape and size with plastic moulded frame of approved make and shade with 6 mm thick hard board backing

Oval shape 450x350 mm (outer dimensions)
Item number
17.32.3
Analysis basis
one no
Priced inputs
8
Derived rate
₹1,377.10/ ONE NO
D-01/RATE ANALYSISITEM 17.32.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.32.3 (Providing and fixing mirror of superior glass (of approved quality) and of required shape and size with plastic moulded frame of approved make and shade with 6 mm thick hard board backing : Oval shape 450x350 mm (outer dimensions)) is derived from 8 priced inputs for one no and works out to ₹1,377.10 per one no after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Hard board 0.45x0.35=0.1575 sqm
  • = 0.1733 sqm say 0.17 sqm
  • Add wastage @ 10% = 0.0158 sqm
ANALYSIS OF RATES · ITEM 17.32.3DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7114MATOvel shape 450x350 mm (outer dimensions) Mirror with Plastic moulded frameOval shape 450x350 mm (outer dimensions) Mirror with Plastic moulded frameeach1319.00319.00
7116MATHard board 6 mm thicksqm0.17124.0021.08
7048MATRawl plug 50 mm (designation 10 no.)Rawl plug 50 mm (designation 10)each424.0096.00
0588MATChromium plated Brass screws 25 mm100 Nos0.04177.007.08
9999MATSundriesL.S.1.432.273.25
9977MATCarriage of materialsL.S.4.162.279.44
0112LABCarpenter 2nd classday0.33816.00269.28
0114LABBeldarday0.33736.00242.88
BUILD-UP TO RATE
TOTAL
968.01
Add 1 % Water charges on “W”
+9.68
TOTAL
977.69
Add GST on “X” (multiplying factor 0.2127)
+207.95
TOTAL
1,185.64
Add 15% CPOH on “Y”
+177.85
TOTAL
1,363.49
Add Cess @ 1% on “Z”
+13.63
Cost of each
1,377.12
SAY
₹1,377.10
D-02/SOURCEPRINTED PAGE 1325
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1325

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1325. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSANITARY INSTALLATIONS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.