Skip to main content

CPWD Analysis of Rates · Sanitary Installations

Providing and fixing mirror of superior glass (of approved quality) and of required shape and size with plastic moulded frame of approved make and shade with 6 mm thick hard board backing

Circular shape 450 mm dia

Item number
17.32.1
Analysis basis
Details of cost for one no.
Priced inputs
8
Derived rate
1,479.05 / one no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.32.1 Providing and fixing mirror of superior glass (of approved quality) and of required shape and size with plastic moulded frame of approved make and shade with 6 mm thick hard board backing : Circular shape 450 mm dia — is derived from 8 priced inputs for one no and works out to ₹1,479.05 per one no after water charges, GST, CPOH and cess. The full build-up is below.

  • Hard board 0.45x0.45 = 0.2025 sqm
  • = 0.2228 sqm say 0.22sqm
  • Add wastage @ 10% = 0.0203 sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
7112Circular shape 450 mm dia Mirror with Plastic moulded frameMaterialeach1436.00436.00
7116Hard board 6 mm thickMaterialsqm0.22124.0027.28
7048Rawl plug 50 mm (designation 10 no.)Rawl plug 50 mm (designation 10)Materialeach224.0048.00
0588Chromium plated Brass screws 25 mmMaterial100 Nos0.02177.003.54
9999SundriesMaterialL.S.1.432.273.25
9977Carriage of materialsMaterialL.S.4.162.279.44
0112Carpenter 2nd classLabourday0.33816.00269.28
0114BeldarLabourday0.33736.00242.88
TOTAL
1,039.67
Add 1 % Water charges on “W”
10.40
TOTAL
1,050.07
Add GST on “X” (multiplying factor 0.2127)
223.35
TOTAL
1,273.42
Add 15% CPOH on “Y”
191.01
TOTAL
1,464.43
Add Cess @ 1% on “Z”
14.64
Cost of each
1,479.07
Say
1,479.05

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1324. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works