Providing and fixing 600x450 mm beveled edge mirror of superior glass (of approved quality) complete with 6 mm thick hard board ground fixed to wooden cleats with C.P. brass screws and washers complete
- Item number
- 17.31
- Analysis basis
- one no
- Priced inputs
- 8
- Derived rate
- ₹1,607.95/ ONE NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.31 (Providing and fixing 600x450 mm beveled edge mirror of superior glass (of approved quality) complete with 6 mm thick hard board ground fixed to wooden cleats with C.P. brass screws and washers complete) is derived from 8 priced inputs for one no and works out to ₹1,607.95 per one no after water charges, GST, CPOH and cess. The full build-up is below.
- 600x450 mm Wooden cleats
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1392 | MAT | Mirror of superior make glass 60x45 cm | each | 1 | 450.00 | 450.00 |
| 7116 | MAT | Hard board 6 mm thick | sqm | 0.27 | 124.00 | 33.48 |
| SUB | Rate as per item no 8.23 of SH : Cladding workRate as per item 8.23 | each | 4 | 40.85 | 163.40 | |
| 0588 | MAT | Chromium plated Brass screws 25 mm | 100 Nos | 0.04 | 177.00 | 7.08 |
| 9977 | MAT | Carriage of materials | L.S. | 4.16 | 2.27 | 9.44 |
| 9999 | MAT | Sundries | L.S. | 1.43 | 2.27 | 3.25 |
| 0112 | LAB | Carpenter 2nd class | day | 0.33 | 816.00 | 269.28 |
| 0114 | LAB | Beldar | day | 0.33 | 736.00 | 242.88 |
- TOTAL
- 1,178.81
- Add 1 % Water charges on “W-A”
- +10.15
- TOTAL
- 1,188.96
- Add GST on “X-A” (multiplying factor 0.2127)
- +218.14
- TOTAL
- 1,407.10
- Add 15% CPOH on “Y-A”
- +186.56
- TOTAL
- 1,593.66
- Add Cess @ 1% on “Z-A”
- +14.30
- Cost of each
- 1,607.96
- SAY
- ₹1,607.95
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1323
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1323. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.