Providing and fixing P.V.C. low level flushing cistern with manually controlled device (handle lever) conforming to IS : 7231, with all fittings and fixtures complete

10 litre capacity - coloured
Item number
17.18.2
Analysis basis
one no
Priced inputs
4
Derived rate
₹1,136.60/ ONE NO
D-01/RATE ANALYSISITEM 17.18.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.18.2 (Providing and fixing P.V.C. low level flushing cistern with manually controlled device (handle lever) conforming to IS : 7231, with all fittings and fixtures complete 10 litre capacity - coloured) is derived from 4 priced inputs for one no and works out to ₹1,136.60 per one no after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (Considering 1 fitter and 1 beldar can fix 8
  • cistern in one day)
ANALYSIS OF RATES · ITEM 17.18.2DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7123MATColoured High density polythylene/ poly propylene 10 lit. (full flush) capacity controlled low level flushing cistern with fittingsColoured High density polyethylene / poly propylene 10 lit. (full flush) capacity controlled low level flushing cistern with fittingseach1583.00583.00
9977MATCarriage of materialsL.S.5.22.2711.80
0116LABFitter (grade 1)day0.125897.00112.13
0114LABBeldarday0.125736.0092.00
BUILD-UP TO RATE
TOTAL
798.93
Add 1 % Water charges on “W”
+7.99
TOTAL
806.92
Add GST on “X” (multiplying factor 0.2127)
+171.63
TOTAL
978.55
Add 15% CPOH on “Y”
+146.78
TOTAL
1,125.33
Add Cess @ 1% on “Z”
+11.25
Cost of each
1,136.58
SAY
₹1,136.60
D-02/SOURCEPRINTED PAGE 1312
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1312

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1312. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSANITARY INSTALLATIONS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.