Providing and fixing P.V.C. low level flushing cistern with manually controlled device (handle lever) conforming to IS : 7231, with all fittings and fixtures complete
- Item number
- 17.18.1
- Analysis basis
- one no
- Priced inputs
- 4
- Derived rate
- ₹1,190.65/ ONE NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.18.1 (Providing and fixing P.V.C. low level flushing cistern with manually controlled device (handle lever) conforming to IS : 7231, with all fittings and fixtures complete 10 litre capacity - White) is derived from 4 priced inputs for one no and works out to ₹1,190.65 per one no after water charges, GST, CPOH and cess. The full build-up is below.
- (Considering 1 fitter and 1 beldar can fix 8
- cistern in one day)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7358 | MAT | Flushing Cistern P.V.C. 10 lts capacity (low level) (White) (with fittings, accessories and flush pipe)Flushing Cistern P.V.C. 10 litre capacity (low level-White) with fittings, accessories and flush pipe | each | 1 | 621.00 | 621.00 |
| 9977 | MAT | Carriage of materials | L.S. | 5.2 | 2.27 | 11.80 |
| 0116 | LAB | Fitter (grade 1) | day | 0.125 | 897.00 | 112.13 |
| 0114 | LAB | Beldar | day | 0.125 | 736.00 | 92.00 |
- TOTAL
- 836.93
- Add 1 % Water charges on “W”
- +8.37
- TOTAL
- 845.30
- Add GST on “X” (multiplying factor 0.2127)
- +179.80
- TOTAL
- 1,025.10
- Add 15% CPOH on “Y”
- +153.77
- TOTAL
- 1,178.87
- Add Cess @ 1% on “Z”
- +11.79
- Cost of each
- 1,190.66
- SAY
- ₹1,190.65
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1312
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1312. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate