Providing and fixing draining board with C.I. brackets including painting of brackets, cutting and making good the walls wherever required

White glazed fire clay draining board of size 600x450x 25 mm
Item number
17.12.1
Analysis basis
one no
Priced inputs
8
Derived rate
₹1,579.65/ ONE NO
D-01/RATE ANALYSISITEM 17.12.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.12.1 (Providing and fixing draining board with C.I. brackets including painting of brackets, cutting and making good the walls wherever required : White glazed fire clay draining board of size 600x450x 25 mm) is derived from 8 priced inputs for one no and works out to ₹1,579.65 per one no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 17.12.1DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7364MATWhite glazed fire clay draining board 600x450x25 mmeach1540.00540.00
1309MATC.I. bracket for wash basin and sinkspair195.0095.00
9999MATCement, sand and grit etc.L.S.13.392.2730.40
9999MATPainting brackets etc.L.S.262.2759.02
9977MATCarriage of materialsL.S.7.82.2717.71
0116LABFitter (grade 1)day0.06897.0053.82
0123LABMason 1st classMason 1st classday0.17897.00152.49
0114LABBeldarday0.22736.00161.92
BUILD-UP TO RATE
TOTAL
1,110.36
Add 1 % Water charges on “W”
+11.10
TOTAL
1,121.46
Add GST on “X” (multiplying factor 0.2127)
+238.53
TOTAL
1,359.99
Add 15% CPOH on “Y”
+204.00
TOTAL
1,563.99
Add Cess @ 1% on “Z”
+15.64
Cost of each
1,579.63
SAY
₹1,579.65
D-02/SOURCEPRINTED PAGE 1307
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1307

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1307. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.