CPWD Analysis of Rates · Sanitary Installations
Providing and fixing white vitreous china laboratory sink with C.I. brackets, C.P. brass chain with rubber plug, 40 mm C.P brass waste and 40mm C.P. brass trap with necessary C.P. brass unions complete, including painting of fittings and brackets, cutting and making good the wall wherever required
Size 450x300x150 mm
- Item number
- 17.11.1
- Analysis basis
- Details of cost for one no.
- Priced inputs
- 13
- Derived rate
- ₹5,020.85 / one no
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.11.1 — Providing and fixing white vitreous china laboratory sink with C.I. brackets, C.P. brass chain with rubber plug, 40 mm C.P brass waste and 40mm C.P. brass trap with necessary C.P. brass unions complete, including painting of fittings and brackets, cutting and making good the wall wherever required : Size 450x300x150 mm — is derived from 13 priced inputs for one no and works out to ₹5,020.85 per one no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1871 | White vitreous china laboratry sink 450x300x150 mmWhite vitreous china laboratory sink 450x300x150 mmMaterial | each | 1 | 1,650.00 | 1,650.00 |
| 1309 | C.I. bracket for wash basin and sinksMaterial | pair | 1 | 95.00 | 95.00 |
| 1315 | C.P.brass chain with 40 mm dia rubber plugMaterial | each | 1 | 37.00 | 37.00 |
| 1952 | C.P. brass waste 40 mmMaterial | each | 1 | 110.00 | 110.00 |
| 1895 | C.P.brass trap40 mm diaC.P. brass trap 40 mm diaMaterial | each | 1 | 347.00 | 347.00 |
| 3617 | C.P.brass union 40 mm diaC.P. Brass union 40 mm diaMaterial | each | 1 | 226.00 | 226.00 |
| 9999 | Red lead, white lead and gaskitMaterial | L.S. | 16.12 | 2.27 | 36.59 |
| 9999 | Cement, sand and grit etc.Material | L.S. | 13.39 | 2.27 | 30.40 |
| 9999 | SundriesMaterial | L.S. | 26.91 | 2.27 | 61.09 |
| 9977 | Carriage of materialsMaterial | L.S. | 13.52 | 2.27 | 30.69 |
| 0116 | Fitter (grade 1)Labour | day | 0.22 | 897.00 | 197.34 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.33 | 897.00 | 296.01 |
| 0114 | BeldarLabour | day | 0.56 | 736.00 | 412.16 |
- TOTAL
- 3,529.28
- Add 1 % Water charges on “W”
- 35.29
- TOTAL
- 3,564.57
- Add GST on “X” (multiplying factor 0.2127)
- 758.18
- TOTAL
- 4,322.75
- Add 15% CPOH on “Y”
- 648.41
- TOTAL
- 4,971.16
- Add Cess @ 1% on “Z”
- 49.71
- Cost of each
- 5,020.87
- Say
- 5,020.85
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1306. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works