Providing and fixing white vitreous china laboratory sink with C.I. brackets, C.P. brass chain with rubber plug, 40 mm C.P brass waste and 40mm C.P. brass trap with necessary C.P. brass unions complete, including painting of fittings and brackets, cutting and making good the wall wherever required
- Item number
- 17.11.1
- Analysis basis
- one no
- Priced inputs
- 13
- Derived rate
- ₹5,020.85/ ONE NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.11.1 (Providing and fixing white vitreous china laboratory sink with C.I. brackets, C.P. brass chain with rubber plug, 40 mm C.P brass waste and 40mm C.P. brass trap with necessary C.P. brass unions complete, including painting of fittings and brackets, cutting and making good the wall wherever required : Size 450x300x150 mm) is derived from 13 priced inputs for one no and works out to ₹5,020.85 per one no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1871 | MAT | White vitreous china laboratry sink 450x300x150 mmWhite vitreous china laboratory sink 450x300x150 mm | each | 1 | 1,650.00 | 1,650.00 |
| 1309 | MAT | C.I. bracket for wash basin and sinks | pair | 1 | 95.00 | 95.00 |
| 1315 | MAT | C.P.brass chain with 40 mm dia rubber plug | each | 1 | 37.00 | 37.00 |
| 1952 | MAT | C.P. brass waste 40 mm | each | 1 | 110.00 | 110.00 |
| 1895 | MAT | C.P.brass trap40 mm diaC.P. brass trap 40 mm dia | each | 1 | 347.00 | 347.00 |
| 3617 | MAT | C.P.brass union 40 mm diaC.P. Brass union 40 mm dia | each | 1 | 226.00 | 226.00 |
| 9999 | MAT | Red lead, white lead and gaskit | L.S. | 16.12 | 2.27 | 36.59 |
| 9999 | MAT | Cement, sand and grit etc. | L.S. | 13.39 | 2.27 | 30.40 |
| 9999 | MAT | Sundries | L.S. | 26.91 | 2.27 | 61.09 |
| 9977 | MAT | Carriage of materials | L.S. | 13.52 | 2.27 | 30.69 |
| 0116 | LAB | Fitter (grade 1) | day | 0.22 | 897.00 | 197.34 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.33 | 897.00 | 296.01 |
| 0114 | LAB | Beldar | day | 0.56 | 736.00 | 412.16 |
- TOTAL
- 3,529.28
- Add 1 % Water charges on “W”
- +35.29
- TOTAL
- 3,564.57
- Add GST on “X” (multiplying factor 0.2127)
- +758.18
- TOTAL
- 4,322.75
- Add 15% CPOH on “Y”
- +648.41
- TOTAL
- 4,971.16
- Add Cess @ 1% on “Z”
- +49.71
- Cost of each
- 5,020.87
- SAY
- ₹5,020.85
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1306
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1306. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.