Providing and fixing Stainless Steel A ISI 304 (18/8) kitchen sink as per IS:13983 with C.I. brackets and stainless steel plug 40 mm, including painting of fittings and brackets, cutting and making good the walls wherever required : Kitchen sink without drain board
- Item number
- 17.10.2.3
- Analysis basis
- one no
- Priced inputs
- 8
- Derived rate
- ₹3,407.20/ ONE NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.10.2.3 (Providing and fixing Stainless Steel A ISI 304 (18/8) kitchen sink as per IS:13983 with C.I. brackets and stainless steel plug 40 mm, including painting of fittings and brackets, cutting and making good the walls wherever required : Kitchen sink without drain board 470x420 mm bowl depth 178 mm) is derived from 8 priced inputs for one no and works out to ₹3,407.20 per one no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7103 | MAT | Stainless steel kitchen sink - without drain board 470x420mm bowl depth 178 mmStainless steel kitchen sink - without drain board 470x420 mm bowl depth 178 mm | each | 1 | 1,272.00 | 1,272.00 |
| 1309 | MAT | C.I. bracket for wash basin and sinks | pair | 1 | 95.00 | 95.00 |
| 9999 | MAT | Cement, sand and grit etc. | L.S. | 13.52 | 2.27 | 30.69 |
| 9999 | MAT | Painting brackets | L.S. | 26.91 | 2.27 | 61.09 |
| 9977 | MAT | Carriage of materials | L.S. | 13.52 | 2.27 | 30.69 |
| 0116 | LAB | Fitter (grade 1) | day | 0.22 | 897.00 | 197.34 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.33 | 897.00 | 296.01 |
| 0114 | LAB | Beldar | day | 0.56 | 736.00 | 412.16 |
- TOTAL
- 2,394.98
- Add 1 % Water charges on “W”
- +23.95
- TOTAL
- 2,418.93
- Add GST on “X” (multiplying factor 0.2127)
- +514.51
- TOTAL
- 2,933.44
- Add 15% CPOH on “Y”
- +440.02
- TOTAL
- 3,373.46
- Add Cess @ 1% on “Z”
- +33.73
- Cost of each
- 3,407.19
- SAY
- ₹3,407.20
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1305
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1305. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.