CPWD Analysis of Rates · Sanitary Installations
Providing and fixing water closet squatting pan (Indian type W.C. pan ) with 100 mm sand cast Iron P or S trap, 10 litre low level white P.V.C. flushing cistern, including flush pipe, with manually controlled device (handle lever) conforming to IS : 7231, with all fittings and fixtures complete, including cutting and making good the walls and floors wherever required
Stainless Steel AISI-304(18/8) Orissa pattern W.C. pan of size 585x480 mm with flush pipe and integrated type foot rests
- Item number
- 17.1.2
- Analysis basis
- Details of cost for one pan
- Priced inputs
- 8
- Derived rate
- ₹11,390.95 / one pan
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.1.2 — Providing and fixing water closet squatting pan (Indian type W.C. pan ) with 100 mm sand cast Iron P or S trap, 10 litre low level white P.V.C. flushing cistern, including flush pipe, with manually controlled device (handle lever) conforming to IS : 7231, with all fittings and fixtures complete, including cutting and making good the walls and floors wherever required: Stainless Steel AISI-304(18/8) Orissa pattern W.C. pan of size 585x480 mm with flush pipe and integrated type foot rests — is derived from 8 priced inputs for one pan and works out to ₹11,390.95 per one pan after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7805 | Salem Stainless steel AISI - 304 (18/8) Orrisa pattern W.C. pan 724mm X 578mmSalem Stainless steel AISI - 304 (18/8) Orrisa pattern W.C. pan 724 mm X 578 mmMaterial | each | 1 | 4,600.00 | 4,600.00 |
| 7358 | Flushing Cistern P.V.C. 10 lts capacity (low level) (White) (with fittings, accessories and flush pipe)Flushing Cistern P.V.C. 10 litre capacity (low level-White) with fittings, accessories and flush pipeMaterial | each | 1 | 621.00 | 621.00 |
| 1896 | 100 mm S.C.I. trap with vent heelMaterial | each | 1 | 358.00 | 358.00 |
| 9999 | Cement, sand and grit etc.Material | L.S. | 26.91 | 2.27 | 61.09 |
| 9977 | Carriage of materialsMaterial | L.S. | 26.91 | 2.27 | 61.09 |
| 0116 | Fitter (grade 1)Labour | day | 1.25 | 897.00 | 1,121.25 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.5 | 897.00 | 448.50 |
| 0114 | BeldarLabour | day | 1 | 736.00 | 736.00 |
- TOTAL
- 8,006.93
- Add 1 % Water charges on “W”
- 80.07
- TOTAL
- 8,087.00
- Add GST on “X” (multiplying factor 0.2127)
- 1,720.10
- TOTAL
- 9,807.10
- Add 15% CPOH on “Y”
- 1,471.07
- TOTAL
- 11,278.17
- Add Cess @ 1% on “Z”
- 112.78
- Cost of each
- 11,390.95
- Say
- 11,390.95
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1281. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.