Providing and fixing Heat Resistant Terrace Tiles (300 mm x 300 mm x 20 mm) with SRI (solar refractive index) > 78, solar reflection > 0.70 and initial emittance > 0.75 on waterproof and sloped surface of terrace, laid on 20 mm thick cement sand mortar in the ratio of 1:4 (1 cement : 4 coarse sand) and grouting the joints with mix of white cement & marble powder in ratio of 1:1, including rubbing and polishing of the surface upto 3 cuts complete, including providing skirting upto 150 mm height along the parapet walls in the same manner

Item number
12.55
Analysis basis
10 sqm
Priced inputs
11
Derived rate
₹1,703.95/ SQM
D-01/RATE ANALYSISITEM 12.55

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.55 (Providing and fixing Heat Resistant Terrace Tiles (300 mm x 300 mm x 20 mm) with SRI (solar refractive index) > 78, solar reflection > 0.70 and initial emittance > 0.75 on waterproof and sloped surface of terrace, laid on 20 mm thick cement sand mortar in the ratio of 1:4 (1 cement : 4 coarse sand) and grouting the joints with mix of white cement & marble powder in ratio of 1:1, including rubbing and polishing of the surface upto 3 cuts complete, including providing skirting upto 150 mm height along the parapet walls in the same manner) is derived from 11 priced inputs for 10 sqm and works out to ₹1,703.95 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Area= 10 sqm+
  • Total=10.30 sqm
  • Cement mortar 1:4 (1 cement : 4 coarse
  • sand)
  • Add wastage @ 3%=0.3 sqm
ANALYSIS OF RATES · ITEM 12.55DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1204MATPrecast heat resistant terrace tiles (size 300x300mm) and 20mm thickPrecast heat resistant terrace tiles (size 300x300 mm) and 20 mm thicksqm10.3465.004,789.50
SUBRate as per Item No.3.9 of SH:MortarRate as per item 3.9cum0.2244,211.70943.42
0367MATPortland Cement (OPC-43 grade)tonne0.0445,156.00226.86
0368MATWhite Cementtonne0.04410,500.00462.00
0875MATRed, chocolate, orange, buff or yellow (red oxide of iron) light shade pigmentRed, chocolate, orange, buff or yellow (red oxide of iron) light shade pigmentkilogram3.0865.00200.20
0124LABMason 2nd classMason 2nd classday1.6816.001,305.60
0115LABCoolieday2736.001,472.00
0139LABSkilled Beldar (for floor rubbing etc.)day1816.00816.00
0101LABBhistiday1816.00816.00
0013MACHMachine for rubbing of floorsday1.6350.00560.00
9999MATSundries including carborandum stone etc.L.S.169.982.27385.85
BUILD-UP TO RATE
TOTAL
11,977.43
Add 1 % Water charges on “W”
+119.77
TOTAL
12,097.20
Add GST on “X” (multiplying factor 0.2127)
+2,573.07
TOTAL
14,670.27
Add 15% CPOH on “Y”
+2,200.54
TOTAL
16,870.81
Add Cess @ 1% on “Z”
+168.71
Cost of 10 sqm
17,039.52
Cost of 1 sqm
1,703.95
SAY
₹1,703.95
D-02/SOURCEPRINTED PAGE 924
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
924

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 924. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.