Providing and fixing Heat Resistant Terrace Tiles (300 mm x 300 mm x 20 mm) with SRI (solar refractive index) > 78, solar reflection > 0.70 and initial emittance > 0.75 on waterproof and sloped surface of terrace, laid on 20 mm thick cement sand mortar in the ratio of 1:4 (1 cement : 4 coarse sand) and grouting the joints with mix of white cement & marble powder in ratio of 1:1, including rubbing and polishing of the surface upto 3 cuts complete, including providing skirting upto 150 mm height along the parapet walls in the same manner
- Item number
- 12.55
- Analysis basis
- 10 sqm
- Priced inputs
- 11
- Derived rate
- ₹1,703.95/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.55 (Providing and fixing Heat Resistant Terrace Tiles (300 mm x 300 mm x 20 mm) with SRI (solar refractive index) > 78, solar reflection > 0.70 and initial emittance > 0.75 on waterproof and sloped surface of terrace, laid on 20 mm thick cement sand mortar in the ratio of 1:4 (1 cement : 4 coarse sand) and grouting the joints with mix of white cement & marble powder in ratio of 1:1, including rubbing and polishing of the surface upto 3 cuts complete, including providing skirting upto 150 mm height along the parapet walls in the same manner) is derived from 11 priced inputs for 10 sqm and works out to ₹1,703.95 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Area= 10 sqm+
- Total=10.30 sqm
- Cement mortar 1:4 (1 cement : 4 coarse
- sand)
- Add wastage @ 3%=0.3 sqm
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1204 | MAT | Precast heat resistant terrace tiles (size 300x300mm) and 20mm thickPrecast heat resistant terrace tiles (size 300x300 mm) and 20 mm thick | sqm | 10.3 | 465.00 | 4,789.50 |
| SUB | Rate as per Item No.3.9 of SH:MortarRate as per item 3.9 | cum | 0.224 | 4,211.70 | 943.42 | |
| 0367 | MAT | Portland Cement (OPC-43 grade) | tonne | 0.044 | 5,156.00 | 226.86 |
| 0368 | MAT | White Cement | tonne | 0.044 | 10,500.00 | 462.00 |
| 0875 | MAT | Red, chocolate, orange, buff or yellow (red oxide of iron) light shade pigmentRed, chocolate, orange, buff or yellow (red oxide of iron) light shade pigment | kilogram | 3.08 | 65.00 | 200.20 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 1.6 | 816.00 | 1,305.60 |
| 0115 | LAB | Coolie | day | 2 | 736.00 | 1,472.00 |
| 0139 | LAB | Skilled Beldar (for floor rubbing etc.) | day | 1 | 816.00 | 816.00 |
| 0101 | LAB | Bhisti | day | 1 | 816.00 | 816.00 |
| 0013 | MACH | Machine for rubbing of floors | day | 1.6 | 350.00 | 560.00 |
| 9999 | MAT | Sundries including carborandum stone etc. | L.S. | 169.98 | 2.27 | 385.85 |
- TOTAL
- 11,977.43
- Add 1 % Water charges on “W”
- +119.77
- TOTAL
- 12,097.20
- Add GST on “X” (multiplying factor 0.2127)
- +2,573.07
- TOTAL
- 14,670.27
- Add 15% CPOH on “Y”
- +2,200.54
- TOTAL
- 16,870.81
- Add Cess @ 1% on “Z”
- +168.71
- Cost of 10 sqm
- 17,039.52
- Cost of 1 sqm
- 1,703.95
- SAY
- ₹1,703.95
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 924
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 924. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.