Providing valleys of 90 cm wide overall in plain G.S. sheet fixed with polymer coated J, or L hooks, bolts and nuts 8 mm dia G.I. limpet and bitumen washers complete

1.60 mm thick with zinc coating not less than 350 gm/m²

Item number
12.5.1
Analysis basis
Details of cost for 9.325m
Priced inputs
10
Derived rate
1,863.90 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.5.1 Providing valleys of 90 cm wide overall in plain G.S. sheet fixed with polymer coated J, or L hooks, bolts and nuts 8 mm dia G.I. limpet and bitumen washers complete : 1.60 mm thick with zinc coating not less than 350 gm/m² — is derived from 10 priced inputs and works out to ₹1,863.90 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • G.I. plain sheets 2.5x0.9m
  • 4 nos. @ 29.95Kg/sheet =119.80Kg.+
  • Total = 122.20 kg. or 1.222q.
  • 25mmx6mm (There are 14 joints)
  • Add 2% wastage = 2.40Kg.
CodeInputUnitQuantityRate (INR)Amount (INR)
0992Galvanised steel plain sheetsMaterialquintal1.2226,800.008,309.60
0222Seam bolts and nuts 6 mm dia and 25 mm longMaterial10 Nos1.211.0013.20
1211G.I. plain washer for seam boltsMaterial100 Nos0.1232.003.84
1208Bitumen washerMaterial100 Nos0.1230.003.60
9977Carriage of bolts, nuts and washersMaterialL.S.0.912.272.07
9999SundriesMaterialL.S.13.522.2730.69
0130MistryLabourday0.4897.00358.80
0102Blacksmith 1st classLabourday1.2897.001,076.40
0103Blacksmith 2nd classLabourday0.8816.00652.80
0114BeldarLabourday2.4736.001,766.40
TOTAL
12,217.40
Add 1 % Water charges on “W”
122.17
TOTAL
12,339.57
Add GST on “X” (multiplying factor 0.2127)
2,624.63
TOTAL
14,964.20
Add 15% CPOH on “Y”
2,244.63
TOTAL
17,208.83
Add Cess @ 1% on “Z”
172.09
Cost of 9.325 metres
17,380.92
Cost of 1.00 metre
1,863.91
Say
1,863.90

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 859. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.