Providing ridges or hips of width 60 cm overall width plain G.S. sheet fixed with polymer coated J or L hooks, bolts and nuts 8 mm dia G.I. limpet and bitumen washers complete

0.63 mm thick with zinc coating not less than 275 gm/m²

Item number
12.4.2
Analysis basis
Details of cost for 10.35 metre long ridge.
Priced inputs
10
Derived rate
980.50 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.4.2 Providing ridges or hips of width 60 cm overall width plain G.S. sheet fixed with polymer coated J or L hooks, bolts and nuts 8 mm dia G.I. limpet and bitumen washers complete 0.63 mm thick with zinc coating not less than 275 gm/m² — is derived from 10 priced inputs for 10.35 metre and works out to ₹980.50 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • G.I.plain sheets 0.63mm thick 1.8x0.9m size
  • 5 nos. @9.23 Kg. per sheet = 46.15 Kg. +
  • Total = 47.07 Kg.
  • 25mmx6mm (There are 14 joints)
  • Add 2% wastage = 0.91 Kg.
  • Say 47 Kg.
CodeInputUnitQuantityRate (INR)Amount (INR)
0992Galvanised steel plain sheetsMaterialquintal0.476,800.003,196.00
0222Seam bolts and nuts 6 mm dia and 25 mm longMaterial10 Nos2.811.0030.80
1211G.I. plain washer for seam boltsMaterial100 Nos0.2832.008.96
1208Bitumen washerMaterial100 Nos0.2830.008.40
9977Carriage of seam bolts and washersMaterialL.S.1.822.274.13
9999SundriesMaterialL.S.13.522.2730.69
0130MistryLabourday0.4897.00358.80
0102Blacksmith 1st classLabourday1.2897.001,076.40
0103Blacksmith 2nd classLabourday0.8816.00652.80
0114BeldarLabourday2.4736.001,766.40
TOTAL
7,133.38
Add 1 % Water charges on “W”
71.33
TOTAL
7,204.71
Add GST on “X” (multiplying factor 0.2127)
1,532.44
TOTAL
8,737.15
Add 15% CPOH on “Y”
1,310.57
TOTAL
10,047.72
Add Cess @ 1% on “Z”
100.48
Cost of 10.35 metres
10,148.20
Cost of 1.00 metre
980.50
Say
980.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 858. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.