Providing ridges or hips of width 60 cm overall width plain G.S. sheet fixed with polymer coated J or L hooks, bolts and nuts 8 mm dia G.I. limpet and bitumen washers complete

0.63 mm thick with zinc coating not less than 275 gm/m²
Item number
12.4.2
Analysis basis
10.35 metre
Priced inputs
10
Derived rate
₹980.50/ METRE
D-01/RATE ANALYSISITEM 12.4.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.4.2 (Providing ridges or hips of width 60 cm overall width plain G.S. sheet fixed with polymer coated J or L hooks, bolts and nuts 8 mm dia G.I. limpet and bitumen washers complete 0.63 mm thick with zinc coating not less than 275 gm/m²) is derived from 10 priced inputs for 10.35 metre and works out to ₹980.50 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • G.I.plain sheets 0.63mm thick 1.8x0.9m size
  • 5 nos. @9.23 Kg. per sheet = 46.15 Kg. +
  • Total = 47.07 Kg.
  • 25mmx6mm (There are 14 joints)
  • Add 2% wastage = 0.91 Kg.
  • Say 47 Kg.
ANALYSIS OF RATES · ITEM 12.4.2DETAILS OF COST FOR 10.35 METRE LONG RIDGE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0992MATGalvanised steel plain sheetsquintal0.476,800.003,196.00
0222MATSeam bolts and nuts 6 mm dia and 25 mm long10 Nos2.811.0030.80
1211MATG.I. plain washer for seam bolts100 Nos0.2832.008.96
1208MATBitumen washer100 Nos0.2830.008.40
9977MATCarriage of seam bolts and washersL.S.1.822.274.13
9999MATSundriesL.S.13.522.2730.69
0130LABMistryday0.4897.00358.80
0102LABBlacksmith 1st classday1.2897.001,076.40
0103LABBlacksmith 2nd classday0.8816.00652.80
0114LABBeldarday2.4736.001,766.40
BUILD-UP TO RATE
TOTAL
7,133.38
Add 1 % Water charges on “W”
+71.33
TOTAL
7,204.71
Add GST on “X” (multiplying factor 0.2127)
+1,532.44
TOTAL
8,737.15
Add 15% CPOH on “Y”
+1,310.57
TOTAL
10,047.72
Add Cess @ 1% on “Z”
+100.48
Cost of 10.35 metres
10,148.20
Cost of 1.00 metre
980.50
SAY
₹980.50
D-02/SOURCEPRINTED PAGE 858
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
858

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 858. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.