Skip to main content

CPWD Analysis of Rates · Roofing

Extra for sunk or raised mouldings in the plaster of Paris (Gypsum anhydrous) ceiling

Item number
12.32
Analysis basis
Details of cost for 10 sqm.
Priced inputs
5
Derived rate
607.45 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.32 Extra for sunk or raised mouldings in the plaster of Paris (Gypsum anhydrous) ceiling — is derived from 5 priced inputs for 10 sqm and works out to ₹607.45 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0869Plaster of ParisMaterialkilogram109.887.00769.16
0122Mason (for plaster of paris work) 1st classLabourday2897.001,794.00
0114BeldarLabourday2736.001,472.00
0101BhistiLabourday0.25816.00204.00
9999Scaffolding and SundriesMaterialL.S.13.522.2730.69
TOTAL
4,269.85
Add 1 % Water charges on “W”
42.70
TOTAL
4,312.55
Add GST on “X” (multiplying factor 0.2127)
917.28
TOTAL
5,229.83
Add 15% CPOH on “Y”
784.47
TOTAL
6,014.30
Add Cess @ 1% on “Z”
60.14
Cost of 10.00 sqm.
6,074.44
Cost of 1.00 sqm.
607.44
Say
607.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 890. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works