Skip to main content

CPWD Analysis of Rates · Roofing

Providing 10 mm thick plaster of Paris (gypsum anhydrous) ceiling up to a height of 5 m above floor level, over first class kail wood strips 25x6 mm with 10 mm gap in between and reinforced with rabbit wire mesh fixed to wooden frame (frame work to be paid separately)

Curved surfaces

Item number
12.31.2
Analysis basis
Details of cost for 10x4.00x2.5=100sqm.
Priced inputs
15
Derived rate
2,067.45 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.31.2 Providing 10 mm thick plaster of Paris (gypsum anhydrous) ceiling up to a height of 5 m above floor level, over first class kail wood strips 25x6 mm with 10 mm gap in between and reinforced with rabbit wire mesh fixed to wooden frame (frame work to be paid separately): Curved surfaces — is derived from 15 priced inputs and works out to ₹2,067.45 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Wooden strips of 1st class kail wood
  • 10x72x40x0.25x0.06 = 432 cudm. +
  • Total = 475.2 cudm
  • required for fixing the laths to frame work
  • including breakage and wastage of nails
  • Rabbit wire mesh required for reinforcement
  • =10x2.5x4 = 100sqm.+
  • Total = 102 sqm.
  • Plaster of paris 10x2.5x4.0x10x1121/1000 = 1121 kg.
  • of the laths10x2.5x4.0x4.0032x1121/1000 = 448.7 kg.
  • Total = 1569.7+
  • Total = 2197.6 kg
  • Add 10% wastage = 43.2 cudm.
  • Add 2% wastage = 2 sqm.
  • Add for plaster of paris joining into the side
  • Add 40% wastage = 627.9
CodeInputUnitQuantityRate (INR)Amount (INR)
1196First class kail wood in planksMaterial10 cudm47.52300.0014,256.00
1219Wire nailsM.S. Wire nailsMaterialkilogram7.558.00435.00
1220Wire mesh (rabbit)M.S. Wire mesh (rabbit)Materialsqm10242.004,284.00
0869Plaster of ParisMaterialkilogram2,197.67.0015,383.20
9977Carriage of wiremesh and nails etc.MaterialL.S.27.32.2761.97
0111Carpenter 1st classLabourday16897.0014,352.00
0114BeldarLabourday16736.0011,776.00
0122Mason (for plaster of paris work) 1st classLabourday32.3897.0028,973.10
0114BeldarLabourday32.3736.0023,772.80
0101BhistiLabourday5.4816.004,406.40
9999ScaffoldingMaterialL.S.839.82.271,906.35
9999SundriesMaterialL.S.538.22.271,221.71
0111Carpenter 1st classLabourday5897.004,485.00
0122Mason (for plaster of paris work) 1st classLabourday10897.008,970.00
0114BeldarLabourday15736.0011,040.00
TOTAL
1,45,323.53
Add 1 % Water charges on “W”
1,453.24
TOTAL
1,46,776.77
Add GST on “X” (multiplying factor 0.2127)
31,219.42
TOTAL
1,77,996.19
Add 15% CPOH on “Y”
26,699.43
TOTAL
2,04,695.62
Add Cess @ 1% on “Z”
2,046.96
Cost of 100 sqm.
2,06,742.58
Cost of 1.00 sqm.
2,067.43
Say
2,067.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 889. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works